1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement
Required? Brick Size 9" 4.5" 3"
Answers were Sorted based on User's Feedback
Answer / hussain
Volume of 1 Brick = 0.230*0.115*0.075 = 0.002
So No of brick req for 1 m3 = (1/0.002) = 500 Nos
1.7 bag of Cement required
0.31 cum sand required for 1 cum of brickwork
Is This Answer Correct ? | 717 Yes | 234 No |
Answer / raja j
brick size in meter=.23*.115*.075 =.0019
add 10 mm mortar for ech sides=(.24*.125*.085)=(.0025)
bricks required for 1 m3 =(1/(0.0025)=400 nos
mortar required =(.0025-.0019)*400=.24
add 15% for wastage = (.24*1.15)=.276m3
so required sand is =.276 m3
cement is =(1440/6)=240*.276= 66 kg
Is This Answer Correct ? | 283 Yes | 134 No |
Answer / ajeet kumr bhatnagar
Actual brick size 230*115*76
So No's of bricks in 1 m3=1÷.23*.115*.076=498nos
Now consider 10mm thick mortar
Now bricks size =240*125*86cm
No's of bricks in 1m3=1/.24*.125*.86=388nos
5% wastge=388+20=418nos actual
Mortar 498-388=110nos bricks
=110*.23*.115*.076=.22m3
30% for dry volume=0.286m3
Wastage 5%=0.015
Net volume=.286+.015=.3(approx)
Cement=.3÷7=0.042=.042÷.0345=1.24 bags
Sand=.042*6=.252m3 or.252*35.28=8.89cft
Is This Answer Correct ? | 161 Yes | 30 No |
Answer / tipu sultan
standard size of brick
=(.19×.09×.09)m
volume of brick
=(.19×.09×.09)m^3
=0.001539
=0.00154m^3
with mortar brick size
=(.20×.10×.10)m
& volume=
=(.20×.10×.10)m^3
=0.002m^3
for volume 0.002m^3 then no. of brick=1
so that
for 1m^3 then nos. of brick = 1÷.002 = 500nos.
Is This Answer Correct ? | 136 Yes | 18 No |
Answer / ajeet kumar bhatnagar
consider brick joint 10mm.
Brick volume 0.23x0.115x0.76=.0020m3
So for 1m3 brick work brick required=1/.0020=500nos
Now taking joint ,volume =.240x.125x0.086=.00245
Now for 1m3 brick work brick require=1/.00258= 388nos
So mortar volume =500-388=112nos brick=112x0.0020=0.32m3
For 1:6 mortar Cement 1/7x0.320=0.0457m3=0.00457/0.0345=1.32bags=1.32x50=66 kg
Sand=6/7x0.32=.274m3x35.28=9.67cft
Is This Answer Correct ? | 67 Yes | 14 No |
Answer / md.furqan anasri
Bricks :395
Cement:1.25 Bags (CPWD)
C-sand:10 cft
Is This Answer Correct ? | 88 Yes | 42 No |
Answer / b.jagan
Per 1m3 B.W required materials
Brick=500mom's
Cement=75kg
Sand=10.5cft
Is This Answer Correct ? | 32 Yes | 14 No |
Answer / asmar ahmed
cement = 1.40 Bags
sand = 10.50 Cft
Bricks = 466 Nos
Is This Answer Correct ? | 33 Yes | 20 No |
# 1. Water observation capacity (MAximum)of Solid bricks # 2. Minimum Crushing Strength of Solid Blocks.
What is diversion tunnel in a dam?
Why there is no use of sea water in producing electricity
why hanger rods are used in beam
how to Concrete cubes testing curing time 7 days casting date 24.05.17 testing date ?
Why Should Curing Not Be Done By Ponding And Polythene Sheets?
what is formula to calculate compressive strength of concrete or procedure??
What is semirigid connections?
m30 mix proportion as per IS code
Requirement of cement, and steel 1:2:4 ratio concrete in 1128 Sqft area(Cement No of bags, steel in Kgs)
what is the cost of per cum of pile foundation?
what is the most suitable foundation when construct a bird watching tower in a marshy land