Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


how much quantity a carpenter do shuttering per day

Answers were Sorted based on User's Feedback



how much quantity a carpenter do shuttering per day..

Answer / sachin

a carpenter can do 3 to 4 sq m shuttering per day

Is This Answer Correct ?    256 Yes 57 No

how much quantity a carpenter do shuttering per day..

Answer / nitin adate

Actually Shuttering output is depend upon type of
structure,height of structure, slab to slab height,shape of
structure, type of shuttering & most important availability
of skilled labour.But for planning purpose 2.5 to 3.00
sqmt /per day ( 1Skilled Carpenter + 2 helper ) is
reasonable value.

Is This Answer Correct ?    106 Yes 31 No

how much quantity a carpenter do shuttering per day..

Answer / aijaz hussain, modi builders

The Out-turn of a Shuttering carpenter per day is between
2.5 sq.m. to 3 sq.m.

Is This Answer Correct ?    64 Yes 27 No

how much quantity a carpenter do shuttering per day..

Answer / m md ali

Formwork-Footings, foundations, ground- Sqm 8
Formwork-Columns, pedestals- Sqm 6
Formwork-Beams and slabs -Sqm 8
Formwork-Tie beams, arches, lintels.
Formwork-Walls- Sqm 12
Formwork-Circular, special shapes -Sqm 4
Formwork- Making timber shutters -Sqm 8

Is This Answer Correct ?    31 Yes 3 No

how much quantity a carpenter do shuttering per day..

Answer / uday gandhi

1CARPENTER + 2 HELPER SHALL GIVE OUTPUT OF 11 SQUARE METERS IN 08 HOURS OF WORK.

Is This Answer Correct ?    92 Yes 67 No

how much quantity a carpenter do shuttering per day..

Answer / arvind rai

4-5 sqm .. which is vey good output.

Is This Answer Correct ?    26 Yes 14 No

how much quantity a carpenter do shuttering per day..

Answer / ghulam raza

4 sq.m in one day  

Is This Answer Correct ?    30 Yes 21 No

how much quantity a carpenter do shuttering per day..

Answer / shaikh shahrukh

4.45 sqm per day.

Is This Answer Correct ?    13 Yes 7 No

how much quantity a carpenter do shuttering per day..

Answer / asif

8 to 12 Sq.M per day,( 1 Carp + 1 Help )

Is This Answer Correct ?    6 Yes 3 No

how much quantity a carpenter do shuttering per day..

Answer / vickey

10 sq.m. per day inclusive slab & beam

Is This Answer Correct ?    44 Yes 44 No

Post New Answer

More Civil Engineering Interview Questions

how much need cement bags for block work of wall approx 1000 hollow blocks 20x20x40cm

0 Answers   MFAR,


Analyze the rate for 1st class brick work in superstructure with 1:6 cement sand mortar. Consider 1000 cu.ft quantity and work out the rate per cu.ft

0 Answers  


what is the mix design for M45 concrete

2 Answers   NDC,


what would be compressive strength of cube for 7 days if design mix of M15

1 Answers  


1) what is the seewage discharge per person per day taken for design purpose as per IS codes? 2) how to convert gauge to MM like if we measure 18G as our door frame then how much is it in MM ? 3) how much binding wire is required ti tie 100kg steel ? 4) while making rings in steel reinforcement , whether the corners of rings are deducted to take out cutting length ? 5) how much carbon content should be there in steel used for construction purpose? 6) what are fe415 & fe 500 and which bars are used in general civil works?

1 Answers  


Which is the indian standard code of line out. ? How much tolerance fot 1 mt lenght? Its challenge....

0 Answers  


it is a corrected question." make a list of engineering property(properties) of soil.

0 Answers   AAI Airports Authority Of India, DLF,


Any bopdy tell me how to prepare rate analysis for Centering and shuttering for RAFT FOUNDATION, SUSPENDED FLOORS, STAIR CASES, RETAINING WALLS, SHEAR WALL and COLUMNS

1 Answers  


Define What is the best type of wood glue?

0 Answers  


que.is ideal size of bricnk use in india,joint size of mortar in massinary ,how many bricks used in 1cum.how to test at site.what is the possition of marka used in bricks?

0 Answers  


the building construction what type of equipments are used in site and its purpose?

1 Answers  


what is weight of asphalt concrete

4 Answers   Schneider,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)