how much quantity a carpenter do shuttering per day
Answers were Sorted based on User's Feedback
Answer / sachin
a carpenter can do 3 to 4 sq m shuttering per day
Is This Answer Correct ? | 253 Yes | 57 No |
Answer / nitin adate
Actually Shuttering output is depend upon type of
structure,height of structure, slab to slab height,shape of
structure, type of shuttering & most important availability
of skilled labour.But for planning purpose 2.5 to 3.00
sqmt /per day ( 1Skilled Carpenter + 2 helper ) is
reasonable value.
Is This Answer Correct ? | 103 Yes | 31 No |
Answer / aijaz hussain, modi builders
The Out-turn of a Shuttering carpenter per day is between
2.5 sq.m. to 3 sq.m.
Is This Answer Correct ? | 63 Yes | 27 No |
Answer / m md ali
Formwork-Footings, foundations, ground- Sqm 8
Formwork-Columns, pedestals- Sqm 6
Formwork-Beams and slabs -Sqm 8
Formwork-Tie beams, arches, lintels.
Formwork-Walls- Sqm 12
Formwork-Circular, special shapes -Sqm 4
Formwork- Making timber shutters -Sqm 8
Is This Answer Correct ? | 30 Yes | 2 No |
Answer / uday gandhi
1CARPENTER + 2 HELPER SHALL GIVE OUTPUT OF 11 SQUARE METERS IN 08 HOURS OF WORK.
Is This Answer Correct ? | 92 Yes | 66 No |
how to calculate the dry wt of sand and cement for a required design mix?for ex:M20
0 Answers Bhugan Infracon, UltraTech,
how to create our resume?
0 Answers Sunraj Construction,
Why the name is "partial safety factor" why not "safety factor"?
0 Answers Engineers India Limited,
In structural steel work what should be the wastage percentage considered to order the material( 200x200x5mm box section) in standard available sizes in India i.e. 6 mtrs?
How much cement is require in one sqft area in a G+3 residential construction.
explain the difference between short column and long column
which is code is used for design of steel structure
In block work seawalls what is the purpose of slip joints?
What are the delays in construction projects due to approvals from owners? How can we analyze them in different prospective? Whats their affects and effects on presently going work?
Why provides hook of stirrups only ones side?
why seismic analysis not done during design of slabs
What are the Design Mix proportion,and where they are used