a) we have 30nos., 300mm dia, 4m length double under
reamed piles.calculate excavation quantity.b) tell
concrete qty. also.
Answer / bharath m
Hai,
Please find the answers below.
a)Excavation quantity
Straight pile = 3.14/4*.3*.3*4*30 = 8.49 Cum. +
Under reamed portion (2 Nos. per pile) = 2*3.14*.318*(.2)*.225*2*30 = 5.39 Cum. Total = 8.49+5.39 = 13.88 Cum.
b)Concrete quantity
as same as item (a) above.
Bharath M
Tamil Nadu
8438238335/9980644165
Is This Answer Correct ? | 3 Yes | 7 No |
how much difference we have to provide when column steel staggered
What does civil engineering mean?
what is the design procedure for building
What"s mean by term of BOQ in construction?
13 Answers Jaypee, Shaarc Projects, Xerox,
As per IS 2502 2(A+B)+24d formula is given for stirrups detailing,but explination not given for how that 24d came
What is the difference between compressive strength and crushing strength?
Reinforced concrete: suppose you are doing rough estimate for purchase of rebar for reinforced concrete slab for single stores residential building. You know total concrete volume will be 100 m3. How many tons rebar 6, 10 and 12mm will you require for the project?
What is the factor of safety in civil engineering
mix design procedure, i.e m15 to m40
when we workout quantities of reinforcement steel , whate are the critari of lap length for column
Give me an example of a time when something you tried to accomplish and failed.
What is the rate of earthwork excavation?