a) we have 30nos., 300mm dia, 4m length double under
reamed piles.calculate excavation quantity.b) tell
concrete qty. also.
Answer / bharath m
Hai,
Please find the answers below.
a)Excavation quantity
Straight pile = 3.14/4*.3*.3*4*30 = 8.49 Cum. +
Under reamed portion (2 Nos. per pile) = 2*3.14*.318*(.2)*.225*2*30 = 5.39 Cum. Total = 8.49+5.39 = 13.88 Cum.
b)Concrete quantity
as same as item (a) above.
Bharath M
Tamil Nadu
8438238335/9980644165
| Is This Answer Correct ? | 3 Yes | 7 No |
How many bricks,sand,cement in 1m3 bricks masonary
3 Answers Ascent, Superior Hi Tech,
How to calculate the quantity of cement mortar 2" for mosaic tile fixing 12"x12"?
how much the ratio of the m15, m25 .......etc
what is period of de-shuttering for different area of slab of M25 grade?
how to calculate the runner (2*3) qty in cft. the length is 8 feet.
6 Answers CCCL, Gammon, Greenko, L&T,
what is mant by point of conter of fracher(p.c.f)
# 1. Size of slit content in sand. # 2. Gravity of sand # 3. Water observation capacity of sand. # 4. minimum crushing Strength of sand.
how many plastr work in one bag cement
how i get all type of short type question answer about civil engg
what"s the abbreviation for P.C.C? what"s the formula to calculate 1m3 P.C.C consumption?
2 Answers ACIL, L&T, Punj Lloyd Ltd, Rajshree Construction,
How much river sand contain the 6 & 10 wheeler truck? Or Maximum sand that any type of truck carry?
1:6 brick masonry cement and sand calculations
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)