what is period of de-shuttering for different area of slab
of M25 grade?
Answers were Sorted based on User's Feedback
Answer / n.c.pathan.
It depends upon the span of the slab. For spans less than
6m we can remeve the props after 14 days and in case of
spans exceeding 6m we can remove the props after a period
of 21 days.
Is This Answer Correct ? | 30 Yes | 5 No |
Material calculation of cm 1:6 for 1sqm
What is code for designing a sheet pile?
Why we use sin wave only in ac not use any other form of wave?
WHAT IS THE IMPORTANCE OF FLY ASH BRICK?
Critical Path Method is...
Where hinge support is used in residential building?
What is steel requirement for one cum concrete
List out the densities of different construction materials such as brick, steel, sand, aggregate etc...
what is the weight of one cubic meter M20 concrete ?
what is formula for concrete mix ratio in m20, m25 and m30?
2 Answers Reddy Veeranna Constructions,
Why we provide hair pin for shed
During reclamation how can the occurrence of mud waves can be rectified?