I've one slab of 24m x 43m. How to calculate required steel
For this slab.
Answers were Sorted based on User's Feedback
LBD= 24 X 43 X 0.125 (SAY, REQUIRED TO ACHIEVE AS PER
DESIGN)= 129 CUM
VOLUME OF STEEL 1% (SAY, REQUIRED TO ACHIEVE AS PER DESIGN
& BBS)= 1.29 CUM= 1.29X 7850 kG= 10126 kG, Apx= 10 Ton.
| Is This Answer Correct ? | 14 Yes | 6 No |
generally it is depending upon the design of slab, becasue
you have such big sapn so there is beam between them. its
depends upon how to design the slab by structral engineer.
generally its depends upon client rquirement.
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / ashok kumar chaudhary
Dear Sir,
SOLUTION :-
Length of Slab = 43M
Width of Slab = 24M
Heigth of Slab = -----(Not Given)
You can not find the quantity of reinforcement .
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / saravanan
hi.
1) length of slab/spacing=no of bar lager side
2) width of slab/spacing=no of bars in shorter side
3) length of one bar = length of slab-(2*cover thickens)
4) length of one bar longer side*total no of bars in longer side(+)length of one bar shorter side*total no of bars=total length of bars requirement in slab
..weight of one meter bar =d^2/162
total weight of bars=total length of bar*weight of bar
| Is This Answer Correct ? | 0 Yes | 0 No |
What is the cost of formwork for columns/beams/rcc walls also what is the cost of shuttering for roof slab at height of 25 feet
do we consider shrinkage factor for calculating cement consumption for CM mixes for different works?
What is mean concrete class c35/20. Here C35 and 20 means?
What are the grade of steel used in the steel design.?
15 Answers Engineers India Limited, L&T,
What is componsation
0 Answers Nagarjuna Construction,
How much concreat we make by 1 bag cement? (ratio- 1:1.5:3 or 1:2:4)
2 Answers Castles Consulting Engineers, KCP, Opaque Infrastructure,
how will calculate the lift load in high rise buildings
What is the proportioning by weight of 1:2:3 concrete mix design of cement, sand, gravel, and water in metric for a 3000 PSI concrete strength and a target slump of 75-100mm?
sir when can we expect the AEE results and when will be the interviews sheduled please guide us in this regard thanking you
WHAR IS DIFFERENCE BETWEEN NOMINAL MIX & DESIGN MIX IN DETAIL
How can I make justification between using concrete grade c35 compare c37?
What is the slope of vertical wall ? quick ans
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)