In 120 m high RCC Chimney shell construction how we can
calculate the inner and outer dia of shell at every +1 m
level as this shell is inclined from bottom to top.
Answers were Sorted based on User's Feedback
Answer / sachin
BY CALCULATING THE SLOPE OF SHELL PER METER AND REDUCING
FROM OUTER AND INER DIA AT EVERY LEVEL WE CAN CALCULATE THE
ACTUAL DIA AT THAT STAGE.
| Is This Answer Correct ? | 14 Yes | 2 No |
Answer / n.c.kapri
in slipform technology ,we do a marking in spur beam from
center.drop the shawal from there and measure the distance
from inner wall to that marking,it will our I.D
ex:marking at 2.9m
distance from inner wall to that marking .475m
so inner dia =2.9+.475
=3.375m
now add the wall thikness in I.D & get outside dia
| Is This Answer Correct ? | 7 Yes | 1 No |
Answer / m.senthilkumar
(bottom outer dia- top outer dia)/ height=average reduce the
dia per 1mt
inner dia =outer dia is checked ok so just measurement wall
thickness is correct or not
example:
bottom outer dia=100mt top outer dia =82mt height=120mt wall
thickness=0.5mt
(100-82)/120=0.15mt each 1mt reduce the dia 0.15mt ok
+4m outer dia=(100-(4*.15))=99.40mt dia
+4m inner dia=(99.40-2*0.5(wall thickness)=98.40mt dia
chimney 90degree maintain =center point maintain 0 to 120mt&
check radius every +1mt
| Is This Answer Correct ? | 2 Yes | 0 No |
Answer / omkar
example:
bottom outer dia=100mt top outer dia =82mt height=120mt wall
thickness=0.5mt
(100-82)/120=0.15mt each 1mt reduce the dia 0.15mt ok
+4m outer dia=(100-(4*.15))=99.40mt dia
+4m inner dia=(99.40-2*0.5(wall thickness)=98.40mt dia
chimney 90degree maintain =center point maintain 0 to 120mt&
check radius every +1mtĀ
| Is This Answer Correct ? | 1 Yes | 1 No |
concrete cube strength if fail 1 no in 7 days .What is the solution
what are co-efficient for jacks, acro spans and runners for slabs per sft?
what are the compressive strength requirements(in 7 days & 28 days) of cement sand mix used for plastering purpose (Cement:sand-1:6)? Kindly give the IS Code reference also.
how can i calculate pcc and rcc cu.mtr rate? specify labor and material cost should be diff
different type of beam
can i place column steel lapping in floor beam? my lapping is 24 inches in floor beam and 24 inches on floor beam
what is temp. control concrete and what use of it ?
contractor receive 100 MT steel.after compliting the work the contractor refund 90 MT steel.How reconsilation of steel done?
WHAT SHOULD BE THE THICKNESS OF CEMENT M-SAND MIXER IN BETWEEN TWO SOLID CEMENT BRICKS USED FOR A HOUSE WALL?
How much sand and cement requirement for 1 SQM 125mm thickness Brickwork
how to design paver block
how to preaper for interview wat they asked in interview give me idea
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)