Answer / pradeep
there is wide range of coeffiecient depends on aspect ratio
of slab, span size, thickness of slab, use of steel plate
of plywood, condition of acrow span and jacks, opening in
slabs, projection in slabs, number of beams and its size
crossing slabs etc. You have to calculate for each building
for one slab than use for typical slab.
Is This Answer Correct ? | 15 Yes | 2 No |
for basic costing, how can we calculate how much amount of steel and cocrete will go in per sqft? and what are the thumbrules?
how can we determine the quantity of steel bars in a structure? is there any formula for determing the number of bars required ?
how to calculate cost of raw materials of a building for 1000 sqft & also consolidated cost of labour in a 1000 sqft building
during site visit if i find voilation going on,what can i do,how i act?
"how can we find the approximate quantity of materials using in a building or total Expenditure in percentage for rough estimate after known the construction area(sqm)".please if you know something about that please post the answer.
why the cracks occurs in NP3 class Hume Pipe ? And what is bearing capacity of it?
waht is the range of compacting factor test result for good concreate?
what is kribs is supporting?
steel which is used for reinforcement and structures why they are directly used why GALVANISATION or PRIMER is not done to prevent from corrosion
How to test cement,sand,20mmbluemetal,40mmbluemetal,bricks,concrete by visual and instrument
0 Answers L&T, R R Thulasi Builders,
what is the size of 50 kg cement bag ? gunny & paper
For 1 cu m of concrete required 1.54 Cu m times dry volume. Pl give clarification of 1.54 factor
1 Answers RASA, Unity Infraprojects,