how must steel will use for 1 cubic meter.formula of steel
for beam,column,lantern.
Answers were Sorted based on User's Feedback
Answer / saif raza
Generally we are consider 100kgs steel per cum of concrete
for calculation which will give the rough quantity of steel
required for project.
Is This Answer Correct ? | 231 Yes | 51 No |
Answer / rajesh kumar jha
Footing - 80 kg/cumec
column - 160 kg/ cumec
Beam. - 110 kg/ cumec
slabe. - 80 kg / cumec
By thomb rule
Is This Answer Correct ? | 119 Yes | 11 No |
Answer / cbsrinivas
for columns 2-3%
for slabs 0.5-1.5%
for beams 1-1.5%
for piles 2-5%
Is This Answer Correct ? | 111 Yes | 31 No |
Answer / arulselvan
for columns 2-3%
for slabs 0.5-1.5%
for beams 1-1.5%
for piles 2-5%..
Example
Lets take example of RCC Column, where reinforcement required is 2 % of concrete volume, weight of steel required will be:
(2/100*1)*7850 (steel density )-per m3 steel-157 kg
Is This Answer Correct ? | 77 Yes | 8 No |
Answer / karthi
for columns 2-3%
for slabs 0.5-1.5%
for beams 1-1.5%
for piles 2-5%..
Please Explain.....?
Is This Answer Correct ? | 48 Yes | 17 No |
Answer / ram punnam
For Footing & Pedastral 1-1.5% of Volume of Concrete
For Columns 2-2.5% of Volume of Concrete
For plinth beam 1.5%-2% of Volume of Concrete
For Roof Beam 2-2.5% of Volume of Concrete
For roof slab 1-1.5% of Volume of Concrete
For RCC Road 0.5-1% of Volume of Concrete
Is This Answer Correct ? | 26 Yes | 14 No |
Answer / utpal panchal
Required steel in concrete is Depend on Types on concreting different structure
For Example,
R.c.c Slab = 0.5 to 1 % steel Required in volume of concrete
R.c.c Beam = 1.8 to 2% % steel Required in volume of concrete
R.c.c column = 2.5 % % steel Required in volume of concrete
R.c.c Road = 0.6 % % steel Required in volume of concrete
(1) Here take Column 1 m3 concrete volume calculation is
(2.5 x 1/100) x 7850 =196.25 kg steel Required
(2) Here take Column 6.90 m3 concrete volume calculation is
( 2.5 x 6.90 /100) x 7850 =1354.12 kg steel Required
Is This Answer Correct ? | 6 Yes | 1 No |
Answer / faisal
100kg per mt3
That gives for slab 4 inches about 100sq ft would require 1 quintal..only a thumb rule ...exact depends on design
Is This Answer Correct ? | 6 Yes | 2 No |
Answer / fahad
4.5 kg per sqft for max 7 floors resistance bldg
Is This Answer Correct ? | 10 Yes | 7 No |
In 1:2:4 ratio how much kgs of cement,fine&coarse aggregates to be used 1cu.m
what is the meaning of M & 20
what affect on the structure and related beam of slab when provide one way slab insteade of two way slab
all rod lapping formula
What is the ratio of Grades M10,M15,M20,M25,M30,M35,M40.
what"s the purpose of dry lean concrete(DLC)and where it"ll be use it?
how much cement consumption in 1 sqmt of wall cleading work (dedo)?
what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?
What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase
How to calculate brick work quantity?? Block work quantity??
how many type of admixtures for water stored structure?
providing, fixing, removal of pockets of size 100*150*300mm to 500*600*1000mm for foundation. the shuttering material used for making &fixing of pockets shall be removed by the contractor without damaged to pockets. if any damage occurred, the same shall be rectified by the contractor is to handover the pockets to forge shop engineer with proper marking of centre lines, levels etc.