how must steel will use for 1 cubic meter.formula of steel
for beam,column,lantern.
Answers were Sorted based on User's Feedback
Answer / mahi
mahi
Required steel in concrete is Depend on Types on concreting different structure
For Example,
R.c.c Slab = 0.5 to 1 % steel Required in volume of concrete
R.c.c Beam = 1.8 to 2% % steel Required in volume of concrete
R.c.c column = 2.5 % % steel Required in volume of concrete
R.c.c Road = 0.6 % % steel Required in volume of concrete
(1) Here take Column 1 m3 concrete volume calculation is
(2.5 x 1/100) x 7850 =196.25 kg steel Required
Is This Answer Correct ? | 2 Yes | 0 No |
Answer / j swati.
As for 1 Cu.m = 7850 kg Steel Required. Take 1% of 7850= Answer Is the 78.50 Kg
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / amit
can anyone plz explain me hoe to calculate it accuratly..
Is This Answer Correct ? | 13 Yes | 19 No |
Answer / marcus
for tendering work we can calculate acc:
foot=40kg/m3
col=175kg/m3
plinth beam=160kg/m3
slab=8kg/m3
beam=130kg.m3
Is This Answer Correct ? | 24 Yes | 33 No |
Answer / mahesha
For footing 80 kg
For pl beam 275 kg
For beam 275 kg
For slab 120 kg
For colomn 375 kg
This is govt design
Otherwise u can take half of this quated steel.
Is This Answer Correct ? | 6 Yes | 15 No |
ratio of rcc 1:1.5:3 grade of concrete ,7days& 14&28 days after curing how much strength of compressive strength in rcc slab
How to calculate the length of chairs provided to support the top rebar in concrete foundation
How calculate the water for 1m3 concrete
cud any one send me tech quest paper(civil engg) at tarizus@yahoo.com
How many Rod required for 58 feet by 24 feet roof slab which is supported by 5 * 3 = 15 Column. Six Stored building Roof Slab = ? Ton 15 Column = ? Ton Slab Beam = ? Ton
we do not provide reinforcement bar through the centre of a column.why?
What is the difference between dumpy level and auto level.
how do we design mix ratio?
You have casted a column above your footing, and you found out it is off its location by 5cm. What would you Do?
wat is meant by aerocon bricks?
If specific gravity of cement is less than 3.15 what is the cause?
What is the difference between Backfilling & Refilling in Earth Work Group Item ?