a)If column dimensions are 250*400mm , what will be
cutting length for 8mm stirrups and how to calculate it? b)
If beam dimensions are 200*400mm , beam coveris 25mm , slab
cover is 20mm , what will be the cutting length for
stirrups? c)Column dimensions are 250*400mm , reinf. is
12nos. bar of 16mm dia , stirrups provided are two legged,
what will be the length of each ring?

Regards

Answers were Sorted based on User's Feedback



a)If column dimensions are 250*400mm , what will be cutting length for 8mm stirrups and how to ca..

Answer / dhivakar

(2A+2B)+8*d
2(320+170)+64 =1044m

Is This Answer Correct ?    1 Yes 3 No

a)If column dimensions are 250*400mm , what will be cutting length for 8mm stirrups and how to ca..

Answer / er shailesh kr srivastava

A)CUTTING LENGTH FOR 8mm Strips=2(250+400-2*80-2*8+24*8)
2(650-160+22*8)
2(490+176)
=1332mm

same as for beam

Is This Answer Correct ?    6 Yes 9 No

a)If column dimensions are 250*400mm , what will be cutting length for 8mm stirrups and how to ca..

Answer / ajay

sir , my name ajay kumar ,working on site i also had the
same problem of estimation , but sir ur answer was so nicely
explained , im very thank full to u for ur valuable and
precious information, sir can i no ur email id and no so i
can get some knowlege from u ?
my email -ajaykapse2@gmail.com

Is This Answer Correct ?    6 Yes 10 No

a)If column dimensions are 250*400mm , what will be cutting length for 8mm stirrups and how to ca..

Answer / ram bhawan

2(A+B)+16*DIA OF STIRRUP BAR

A = INNER HEIGHT OF STIRRUP
B = INNER BREATH OF STIRRUPS

IF CLEAR COVER IS GIVEN (COVER GIVEN FROM STIRRUP NOT FROM
MAIN BAR)

Is This Answer Correct ?    2 Yes 9 No

a)If column dimensions are 250*400mm , what will be cutting length for 8mm stirrups and how to ca..

Answer / silpa

250-25+8=233mm,
400-25+8=383mm
2(0.233+0383)+16*0.08=2.512m

Is This Answer Correct ?    9 Yes 32 No

a)If column dimensions are 250*400mm , what will be cutting length for 8mm stirrups and how to ca..

Answer / anthony victor bernard

a)250-column cover both side+8*dia of rod
400-column cover both side+8*dia of rod
so cutting length is (.200+.350)*2+(2*5*.008)
=1.180 mts
(b)cutting length is (.150+.355)*2+(2*5*.008)
=1.090 mts
(c)cutting length is (.100+.350)*2+(2*5*.008)
=0.980 mts

Is This Answer Correct ?    11 Yes 38 No

a)If column dimensions are 250*400mm , what will be cutting length for 8mm stirrups and how to ca..

Answer / neelakantam

a)250-column cover both side+8*dia of rod
400-column cover both side+8*dia of rod
so cutting length is (.250+.400)*2-.160+.128
=1.268 mts
same as (b)

Is This Answer Correct ?    37 Yes 65 No

Post New Answer

More Civil Engineering Interview Questions

How to calculate the Qty of Mortar in 1 m3 Brick work? Detailed Calculation Required?

4 Answers  


among the strectcher, header, english and flemish bond which has greater strength? where these bonds are preferred?????

3 Answers  


what is a moment connection and shear connection ? where it provided ? why it provided ?

1 Answers  


how to calculate weight of round steel bar and square steel bar, i section bar and c channel bar, angle bar

2 Answers  


what is isoseismal?

1 Answers  






Define Who designed the city of Washington DC?

0 Answers  


20mm thick sand face plaster on walls consisting of 12 mm the backing coat of c.m.(1:3)and 8mm thick finished coat of c.m.(1:1)including scaffolding, watering, finishing etc complete please calculator with methyl et et r u

0 Answers   Dhruv Construction,


If i buy some material and the seller asks me my TIN number what does that mean?? Is it my Taxpayers Identification number or it is my Tax invoice number? What does both of these stands for???

2 Answers   Simplex,


What is Refuse Area ? And What is Definition ?  

2 Answers  


is there any thumb rule for calculating construction cost of the building with pile foundation per sft. area?

0 Answers  


convert 1cum how many kilo

7 Answers  


what will be the quantity of following materials in P.C.C for the total area of (100'x70'x 0'4") 1)NO. OF CEMENT BAGS 2)SAND IN CU.FT 3)METTLE IN CU.FT

0 Answers   Pratibha Industries,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)