a)If column dimensions are 250*400mm , what will be
cutting length for 8mm stirrups and how to calculate it? b)
If beam dimensions are 200*400mm , beam coveris 25mm , slab
cover is 20mm , what will be the cutting length for
stirrups? c)Column dimensions are 250*400mm , reinf. is
12nos. bar of 16mm dia , stirrups provided are two legged,
what will be the length of each ring?
Regards
Answer Posted / silpa
250-25+8=233mm,
400-25+8=383mm
2(0.233+0383)+16*0.08=2.512m
Is This Answer Correct ? | 9 Yes | 32 No |
Post New Answer View All Answers
In block work seawalls what is the purpose of slip joints?
Why Is Propping Required For Long Structures Once The Form Work Is Removed?
what is difference between fluidity and workability also how palsticizer works
What is progress payment?
What is the density of Fiber reinforced concrete and give me the which fibers we can use in Concrete?
What is the purpose of Chipping in the heavy foundation?
what is the price of a cubic meter of concrete on international market?
Need help in designing a degasser tower for 2m3/hr DM plant, also send me the formulae used
Explain what are the problems one might face while having a Cantilever balcony?
what is anchorage length,lap length and (dont remember the last one)
how ratio is calculated for any grade of concrete. for e.g. sppose M20 requires(x;y:z) quantity of cememt sand and aggregate.
How to calculate sand , cement quantity for 23mm thk brick work(10x10)
calculate the quantity of cement ,sand,bars and aggregate used for 28*4 ft with 4 inch (125mm) thick
which formula used for calculate the area of segmental arch?
for pretensioning which will yield first and same for post tensioning?