Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


how much brick,cement,and sand required in 1cum
brickwork(1:4)

Answers were Sorted based on User's Feedback



how much brick,cement,and sand required in 1cum brickwork(1:4)..

Answer / manoj mall

for brick size 230mmx115mmx75mm (1:4) for 1cum
volume of 1 brick= 0.00198
say 12mmtk mortar on brick layer
so vol of brick 0.00267 cum
No. of bricks in 1cum = 1/0.00267 = 375 num bricks
volume of bricks for 1cum = 375x0.00198=0.724 cum
volume of cement mortar 1~0.724=0.26cum
add 15% for wastae=0.3 cum
add 30% for dry mortarof 0.3 cum = 0.4 cum
for cm 1:4 = 1+4=5
qnty of cement 1/5 x 0.4 = 0.08 cum
1 bag of cement = 0.035 cum
0.08/0.035 = 2.28 bag
sand = 0.08 x 4 = 0.32 cum

Is This Answer Correct ?    188 Yes 48 No

how much brick,cement,and sand required in 1cum brickwork(1:4)..

Answer / ashok yadav

The actual size of brick is 230 mm x 110 mm x 75 mm
Volume of one brick = 0.0018975 cum
For calculation take a wall of size 10.00 mtr long and 3.00 mtr height 230mm thick wall
Volume of wall = 6.90 Cum
No of course with 10mm thick mortar = 3.00/0.085 = 35 coarses
No of bricks in one coarse 10.00/0.24 = 41.67x2 =83 nos
Total no of bricks in wall = 83x35 = 2905 bricks
No of bricks in one cum = 2905/6.9 = 421 Bricks
Total volume of Bricks = 421x0.0018975 = 0.798 Cum
Volume of Mortar = 1.00-0.798 = 0.202 Cum
Add Wastage 15 % = 0.2323 Cum
Add Bulkage dry to wet mortar 25% = 0.29 Cum Say 0.30 Cum
If Mortar ratio is 1:6 then Cement = (0.30/7)x28.8 Bags= 1.23 Bags
Sand = (0.30/7)x6 Cum = 0.0.257 Cum= 9.0 Cft
If Ratio is 1:4 then Cement = (0.30/5)x28.8 Bags= 1.72 Bags
Sand = (0.30/5)x4 Cum = 0.24 Cum = 8.5 Cft
Sand

Is This Answer Correct ?    12 Yes 3 No

how much brick,cement,and sand required in 1cum brickwork(1:4)..

Answer / suyog patil

for brick size 200mmx100mmx100mm (1:4) for 1cum
volume of 1 brick= 0.002
say 12mm thick mortar on brick layer
so volume of brick=0.00267 cum
No. of bricks in 1cum = 1/0.002 = 500 no. bricks
volume of bricks for 1cum = 500x0.00154=0.77 cum
volume of cement mortar 1-0.766=0.23cum
add 15% for waste=0.26 cum
add 30% for dry mortar of 0.3 cum = 0.34 cum
for cm 1:4 = 1+4=5
quantity of cement 1/5 x 1 x 0.34 = 0.068 cum
1 bag of cement = 0.035 cum
0.068/0.035 = 1.94 i.e 2 bag
sand =1/5 x 4 x 0.34= 0.27 cum

Is This Answer Correct ?    6 Yes 4 No

how much brick,cement,and sand required in 1cum brickwork(1:4)..

Answer / suneel.p

brick size 0.23*0.1*0.1(1:4)
valum of brisk : 0.0023cum
say 12mm thick mortar or brick layar((0.23+.0006)*(0.1+.0006)*(0.1+.0006)
so volume of brick: 0.00265
no.of bricks in 1cum=1/0.00265=378 no.s
volum of brik for 1cum=378*0.0023=0.869cum
volum of mortar 1-0.869=0.131
add30% for dry mortar of =0.30cum
add 10% for wastages =0.10cum

total volum of mortar =0.40 cum
for c:m =1+4=5
qantay of cemant 1/5*0.4=0.08 cum
1cum of cemant =(1440/50)=28.8bags
=.08*28.8=2.304bags
sand =4/5=0.8*0.4=0.32cum

Is This Answer Correct ?    16 Yes 19 No

how much brick,cement,and sand required in 1cum brickwork(1:4)..

Answer / a.sanjeeva karna

brick size 0.23*0.1*0.1(1:4)
valum of brisk : 0.0023cum
say 12mm thick mortar or brick layar((0.23+.006)*(0.1+.006)*
(0.1+.006)
so volume of brick: 0.00265
no.of bricks in 1cum=1/0.00265=378 no.s
volum of brik for 1cum=378*0.0023=0.869cum
volum of mortar 1-0.869=0.131
add30% for dry mortar of =0.170 cum
add 10% for wastages =0.013 cum

total volum of mortar =0.183 cum
Say =0.200 Cum
for c:m =1+4=5
qantay of cemant 1/5*0.2=0.04 cum
1cum of cemant =(1440/50)=28.8bags
=.04*28.8= 1.152bags
sand =4/5=0.8*0.2=0.16cum

Is This Answer Correct ?    6 Yes 10 No

how much brick,cement,and sand required in 1cum brickwork(1:4)..

Answer / er. anil kumar

brick size - .23*.115*.075
1 cum dry volume of mortar- .30
mortar ratio -1:6
for cement-.3*1/7 =.042cum
1 cum of cement - 28.8 bags
for cement- .042*28.8= 1.23 bags
for send - .30*6/7= .257cum

Is This Answer Correct ?    7 Yes 11 No

how much brick,cement,and sand required in 1cum brickwork(1:4)..

Answer / pradip mahato

Brick size 230mmx115mmx75mm (1:4)
volume of 1 brick= 0.00198cum
say 10mmthk mortar on brick layer
so vol of 1 brick 0.00255 cum
No. of bricks in 1cum = 1/0.00255 = 393 num bricks
volume of bricks for 1cum = 393x0.00198=0.778 cum
volume of cement mortar 1-0.778=0.22cum
add 15% for wastae=0.15 cum
add 30% for dry mortarof 0.3 cum
total=.15+.3=0.45cum
for cm 1:4 = 1+4=5
qnty of cement 1/5 x 0.45 = 0.09 cum
volume of 1 bag cement = 0.035 cum
cement=0.09/0.035 = 2.571 bag
sand = 4/5 x0.45 = 0.36 cum =12.715cft

Is This Answer Correct ?    7 Yes 12 No

how much brick,cement,and sand required in 1cum brickwork(1:4)..

Answer / suman kumar

cement =1.15 bags
send = 9.18 cft
Brick = 500 nos

Is This Answer Correct ?    21 Yes 30 No

Post New Answer

More Civil Engineering Interview Questions

what is the least count of auto level staff

14 Answers  


sir iam dng my engg final yr (civil) iam intrested to write group_1 .if we write this exam what kind of jobs we get and what should be the minimum score for us to get qualified and iam having reservation too.

0 Answers  


What is cold joint, what will happen due to cold joint?

1 Answers  


How do you find the weight of rod per metre lenth ?

18 Answers   CCCL,


what is the most suitable foundation when construct a bird watching tower in a marshy land

0 Answers  


Mean of m25 concrete

8 Answers   Artech, Dream Careers, KND Engineering, L&T, Trans Concrete,


what is the painting co efficient of slope roof tiles?

0 Answers  


what is the formula to calculate costing of rubble soling and wbm in road works?

1 Answers  


General Knowledge 1. Which is the virus for SWINE Flu? Ans.H1N1 virus 2. Who is Paola Maino? a) Original Name of Sonia Gandhi. b) Mother Name of Sonia Gandhi c) An actress d) Christian Missionary 3. Who is Andy Moles? 4. Which state there is no scheduled caste seat for lok Sabha Assembly? CIVIL ENGINEERING 1. When was Indian road Congress (IRC) established? 2. What is the camber for Concrete Road? 3. What is the camber to be provided for Earth Road? 4. What is the ruling gradient to be provided for Plain roads? 5. What is the type of surveying to be used for deciding the alignment of hilly roads? 6. What is the condition on which Bernoulli law depends? 7. water is which type of fluid a)Newtonian b)Non- Newtonian c)Ideal d)Compressive 8. The law of continuity depends upon what factors? 9. In Plane Table surveying which is done first a) centering b)Leveling c)Orientation d)Centering and leveling simultaneously 10. Pavement width depends upon a)Type of terrain b) lane width c)Type of traffic 11. Which is costliest type of timber a) Sal b) Shish am c) Teak? 12. Which is timber used for making plywood a)Teak c) Bamboo fibers d)Common Timber 13. What is Veneering?

6 Answers   Vizag Steel, VSP,


how to calculate quantity of cement and sand for plastering works in CM 1:6 proportion.....plz answer anyone.....and write the formula...

4 Answers  


design mix for M15,M20, M25,M30 please

2 Answers   CIDC, Design Ideas,


What is the difference between first angle projection and third angle projection?

9 Answers   CLG, Elecon, JTEKT, Nagarjuna Construction,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)