Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how much brick,cement,and sand required in 1cum
brickwork(1:4)

Answer Posted / a.sanjeeva karna

brick size 0.23*0.1*0.1(1:4)
valum of brisk : 0.0023cum
say 12mm thick mortar or brick layar((0.23+.006)*(0.1+.006)*
(0.1+.006)
so volume of brick: 0.00265
no.of bricks in 1cum=1/0.00265=378 no.s
volum of brik for 1cum=378*0.0023=0.869cum
volum of mortar 1-0.869=0.131
add30% for dry mortar of =0.170 cum
add 10% for wastages =0.013 cum

total volum of mortar =0.183 cum
Say =0.200 Cum
for c:m =1+4=5
qantay of cemant 1/5*0.2=0.04 cum
1cum of cemant =(1440/50)=28.8bags
=.04*28.8= 1.152bags
sand =4/5=0.8*0.2=0.16cum

Is This Answer Correct ?    6 Yes 10 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is the procedure and technnology behind jointing of prestessed block in Delhi metro rail project.

2603


what are the ffactors you considered choosing the course?

2194


how we calculate the vol.of wet concrete..?

1899


With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr

2463


How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.

1526


any book or article on pumped concrete.

2220


What is rate for brick masonry work of 1.0 m3 in cm 1:6?

1187


sir i want to know that in L & T construction can we do our 6 months training proggramme cum placement???????

2269


What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.

2104


whaat is blister in box girder bridge and what is its function..

4941


how to find ssm in foundation?

1949


What is the density of DLC & PQC and how it is differ from normal concrete?

3749


Coverage of 25mm.thick ratio of 1:4 cement mortar?

1915


3. A vane 12.5 cm long, 8.8 cm dia was pressed into a soft clay at the bottom of borehole. Torque was applied and the value at failure was 55 N-m. find the shear strength of the clay on a horizontal plane.

2144


How to determine thee cut length for steel reinforcement bars in R.C.C design

1571