how much brick,cement,and sand required in 1cum
brickwork(1:4)
Answer Posted / pradip mahato
Brick size 230mmx115mmx75mm (1:4)
volume of 1 brick= 0.00198cum
say 10mmthk mortar on brick layer
so vol of 1 brick 0.00255 cum
No. of bricks in 1cum = 1/0.00255 = 393 num bricks
volume of bricks for 1cum = 393x0.00198=0.778 cum
volume of cement mortar 1-0.778=0.22cum
add 15% for wastae=0.15 cum
add 30% for dry mortarof 0.3 cum
total=.15+.3=0.45cum
for cm 1:4 = 1+4=5
qnty of cement 1/5 x 0.45 = 0.09 cum
volume of 1 bag cement = 0.035 cum
cement=0.09/0.035 = 2.571 bag
sand = 4/5 x0.45 = 0.36 cum =12.715cft
Is This Answer Correct ? | 7 Yes | 12 No |
Post New Answer View All Answers
undistributed samples are obtained by
how to frame the sentence in voucher pad ? Description : 1.Food Expenses during site visit 2.Stamp Paper approval expenses 3.Travelling expenses 4. sweet distribution
What tor stands for in tor steel?
What are the different methods for drawing an arc?
what is the water cement ratio for plastering
What is command line?
What is meant by a context menu in a cad software?
What is reinforced concrete?
how many sqft or cft of work done by a mason per day in all works such as brick,block,concrete,shuttering carpenter,reinforcement fabricator,painter,door window carpenter.....everything thank you
do you think we shall remove un wanted soil for foundation excavation even if the thickness of the soil strata is more than 8m ?
where tie beam is used? what is the pupose? what dimension of tie beam can provided and number and diameter of steel bars to be used between the columns of 1333mm and 1400.
Suggest how many column, beem, etc required for 30 mtrs x 21 mtrs width x 8mtrs height for industrial shed of ground floor. I want to know the quantity of tmt steel consumption and Concrete consumption for budgeting
load combinations how many types for staad design purpose?
What is labor and material payment bond?
what is box type waterproofing and how it is exsiccated and what is the method of doing box type waterproofing