what is the proportion of m20 grde concrete? also how much
water is required for this proportions? As there were any
formula for water-quantity?

Answers were Sorted based on User's Feedback



what is the proportion of m20 grde concrete? also how much water is required for this proportions?..

Answer / upendra

Proportion for M20 grade concrete is 1:1.5:3 , water to be
added is as per water cement ratio 0.54 i.e
0.54 X 50kg of cement wt = 27lit.

Is This Answer Correct ?    25 Yes 7 No

what is the proportion of m20 grde concrete? also how much water is required for this proportions?..

Answer / suraj

water required in concrete is 28%of cement and 5% of total aggregate.

Is This Answer Correct ?    9 Yes 3 No

what is the proportion of m20 grde concrete? also how much water is required for this proportions?..

Answer / pinku gautam

A water/cement ratio of only 0.38 is required for complete
hydration of cement. (Although this is the theoretical limit, water cement ratio lower than
0.38 will also increase the strength, since all the cement that is added, does not hydrate)
Water added for workability over and above this water/cement ratio of 0.38, evaporates
leaving cavities in the concrete. These cavities are in the form of thin capillaries. They
reduce the strength and durability of concrete. Hence, it is very important to control the
water/cement ratio on site. Every extra lit of water will approx. reduce the strength of
concrete by 2 to 3 N/mm2 and increase the workability by 25 mm

Is This Answer Correct ?    2 Yes 1 No

Post New Answer

More Civil Engineering Interview Questions

what are IS code for M20, 25, etc

40 Answers   Aarvi Encon, Best Builders, L&T, NCC, PWD, RNS, Vardhman,


How much sand for a 107sqm residensial building

1 Answers   Shapoorji Pallonji Group(SPCL),


what is studds? where it can be done?

1 Answers  


How many are the types of joints?

0 Answers  


what is the minium content of cementous material per cu meter

2 Answers  






what is project planning

2 Answers   NCC,


How to calculate plastering for elevated water storage tank

0 Answers  


what is the percentage of Fly Ash content in cement and in concrete?

5 Answers  


stub column means

5 Answers  


what is the sp.gravity of sand?

3 Answers  


What is the cost difference between site mix and ready mix concrete per cubic meter

0 Answers   L&T,


how material can be calculate for brick work in 1:6

3 Answers   L&T,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)