Any bopdy tell me how to prepare rate analysis for
Centering and shuttering for RAFT FOUNDATION, SUSPENDED
FLOORS, STAIR CASES, RETAINING WALLS, SHEAR WALL and COLUMNS
Answer / praman kumar srivastava
Providing, erecting, fixing in position striking/ removing
and cleaning shuttering and centering for formwork in
foundation and Plinth at all locations for all shapes
inclufing chamfers, camber, splays, keys, wedges, props,
rail, bracing , brackets, cutti
Foundation. For 10.8 Sqmt Area (Based on Physical Analysis)
Material :
Ply Wood Sqmt 11.000 538.000 5918.000
Nut Bolts, Balli Battens etc LS
1095.000
For 15 Repetation 7013.000
For 1 467.533
Labour :
Carpenter I Class Nos 0.750 175.000 131.250
Beldar skilled Nos 1.500 135.000 202.500
Shuttering Oil LS 1.000 33.400 33.400
Sundries I Time 16.700 1.690 28.223
862.906
Add for water charges @ 1%
8.629
Total 871.535
Add for contractor's profit and overheads @ 10%
148.161
Cost for 10.8 sqm 1019.696
Cost of 01 Sqmt 94.416
Say 94
Is This Answer Correct ? | 7 Yes | 2 No |
Providing and casting in situ cement concrete M-25 of trap/granite/quartzite/gneiss metal for rcc, Providing formwork,Curing the concrete and Complete. what is rate per Cum. and what is rate for M-30 Grade Concrete.
how statics is different from dynamics
how to convert kg/m3 to kg/cft
how much least count of levelling ?
how to calculate the steel quantity for columns and beams
I am a civil engineer . I am also selected for sbi clerk interview which is to be held on 4th May2010 is there anybody resembling the same? what question can be asked and what should be the probable answers?
What in bending moment, if a moment is free end of cantilever beam?
plumbing CPVC fitting FTE Brass full form
hi i am kailash we construction start a slab load baring 40feet *9 feet *4 inch plz suggest matarials and qty
How calculate Load Bearing Capacity of Soil?
In a beam tension is always at the bottom but sometimes when we design using staad we get more number of rebars at the top compression zone Why?
what"s the M book?