how to calculate 1:2:4 ratio concrete cement, sand, metal
and water please give me brief calculation

Answers were Sorted based on User's Feedback



how to calculate 1:2:4 ratio concrete cement, sand, metal and water please give me brief calculati..

Answer / himanth kumar

Consider for 1CUM of concrete is to be prepare,For that

M15 is a nominal mix, its proportion is 1:2:4

for 1cum of final mix(Dence) is required, 1.50 to 1.55 Cum
of loose ingredients with the required proportion we want
to add.

Based on that take avg of 1.50 & 1.55 is 1.52

Total proportion = 1+2+4 = 7

For Cement Qty = 1.52/7=0.217 Cum of cement required to
prepare 1Cum of M15 concrete.But cement is always taken in
Weight.For that the unit weight of cement is 1440 KG/Cum
Total cement required = 0.217x1440= 312.68 Kgs.

Sand = 0.217 x 2 =0.434 Cum

Metal or Aggregate = 0.217 x 4 =0.868 Cum.

Is This Answer Correct ?    1120 Yes 173 No

how to calculate 1:2:4 ratio concrete cement, sand, metal and water please give me brief calculati..

Answer / adishankar (quantity surve

DETAILS:

cement = 1,
sand = 2
metal = 4
so wat is the ratio we want mixing (1:2:4)=1+2+4=7
7 is mixing propotion
volume of wet cement conceret is 1.54 to 1.57

unit weigth of cement is 1440kg/cum

one bag of cement =50/1440=0.034722 cum

solution : cement = 1.54/7=0.22
0.22/0.03472=6.33 bags
one bag of cement = 50kgs
=6.33*50kgs=316.82 kgs

solution of sand = 0.22*2=0.44cum

2 is the mixing of propotion

soolution of metal = 0.22*4=0.88cum

4 is the mixing of propotion

say i cum of cement conceret 1:2:4 ratio

cement = 6.33 bags

sand = 0.46 cums

metal = 0.88 cums


this is one type of solution

unit weight of cement is 1440kg/cum
sand 1660 to 1800kg/cum
Unit weight of metal is 1630kg to 2000kg/cum

so cenment = 1.54/7=0.22
0.22*1440=316.8 kgs/cum
sand = 0.22*1750=385kgs/cum

metal = 0.22*2000=440kgs/cum

Is This Answer Correct ?    554 Yes 92 No

how to calculate 1:2:4 ratio concrete cement, sand, metal and water please give me brief calculati..

Answer / pinkal

Here volume is (1 cement bag=1.25 cu.ft)
cement 1 1.25 cu.ft
sand 2 2.50 cu.ft
metal 4 5.00 cu.ft
-----------
8.75 cu.ft total volume

Is This Answer Correct ?    716 Yes 336 No

how to calculate 1:2:4 ratio concrete cement, sand, metal and water please give me brief calculati..

Answer / raja babu.k

Sample = 1 M3 of M15 i.e 1:2:4

Aggregate = 20mm

Final Mixture and Loose Aggregate Ratio is 1.57(in practies)

SO CALCULATION FOR 1:2:4

1+2+4=7

CEMENT = (1.57/7)X1=0.2242 M3X1440=322.8Kg= 6.45 Bags
RIVER SAND= (1.57/7)X2=0.4485 M3X35.314 = 15.83 Cft
AGGREGATE = (1.57/7)X4=0.8971 M3X35.314 = 31.68 Cft

Is This Answer Correct ?    220 Yes 43 No

how to calculate 1:2:4 ratio concrete cement, sand, metal and water please give me brief calculati..

Answer / sjtbehera

The ratio is 1:2:4, so total ratio is 1+2+4=7
considering 1cum.
cement = (1 x 15.4)/7= 2.2 cum
= 2.2/.347=6.3bags
sand=2.2x2=4.4cum
metal=2.2x4=8.8cum

Is This Answer Correct ?    380 Yes 252 No

how to calculate 1:2:4 ratio concrete cement, sand, metal and water please give me brief calculati..

Answer / arun

DETAILS:

cement = 1,
sand = 2
metal = 4
so wat is the ratio we want mixing (1:2:4)=1+2+4=7
7 is mixing propotion
volume of wet cement conceret is 1.54 to 1.57

unit weigth of cement is 1440kg/cum

one bag of cement =50/1440=0.034722 cum

solution : cement = 1.54/7=0.22
0.22/0.03472=6.33 bags
one bag of cement = 50kgs
=6.33*50kgs=316.82 kgs

solution of sand = 0.22*2=0.44cum

2 is the mixing of propotion

soolution of metal = 0.22*4=0.88cum

4 is the mixing of propotion

say i cum of cement conceret 1:2:4 ratio

cement = 6.33 bags

sand = 0.46 cums

metal = 0.88 cums


this is one type of solution

unit weight of cement is 1440kg/cum
sand 1660 to 1800kg/cum
Unit weight of metal is 1630kg to 2000kg/cum

so cenment = 1.54/7=0.22
0.22*1440=316.82 kgs/cum
sand = 0.44*1750=770kgs/cum

metal = 0.88*2000=1760kgs/cum

Is This Answer Correct ?    92 Yes 21 No

how to calculate 1:2:4 ratio concrete cement, sand, metal and water please give me brief calculati..

Answer / sandeepthakur1981

for 01 cu.m.

cement=1.52/7 =.217
= .217x30= 6.51 bags.

sand= .217x2= 0.434cu.m

aggregate= .217x4= 0.868cu.m

Is This Answer Correct ?    94 Yes 35 No

how to calculate 1:2:4 ratio concrete cement, sand, metal and water please give me brief calculati..

Answer / the engineer

In order to estimate the quantity of loose materials to have
100 cubic feet wet concrete we first multiply the wet
concrete by 1.54.
e.g 100x1.54=154 cubic feet of dry materials we need.

now come to the ratio of concrete which is 1:2:4 so sum of
the ratio will be 1+2+4=7

calculating separately each material:

Cement: 1/7x154 = 22 cubic feet
where 1 bag of cement measured 1.25 cubic feet approx
therefore 22/1.25 = 17.6 bags of cement. 1 bag contains 50kg
cement so total cement by weight we need for 100 cubic feet
concrete = 17.6x50 = 880kgs

sand: 2/7x154 = 44 cubic feet

coarse aggregate: 4/7x154 = 88 cubic feet

Is This Answer Correct ?    59 Yes 15 No

how to calculate 1:2:4 ratio concrete cement, sand, metal and water please give me brief calculati..

Answer / m

ratio is 1:2:4
1+2+4=7

100cft concrete
100*1.54=
then divide by 7
then divide by 1.25 you wil have cement bag

Is This Answer Correct ?    71 Yes 29 No

how to calculate 1:2:4 ratio concrete cement, sand, metal and water please give me brief calculati..

Answer / chetan khairnar

Note: For 1m3 wet concrete = 1.52m3 dry concrete approximately
SP.Wt of concrete= 1440 kg/m3 (or) 1.44 t/m3
1 bag of cement = 50 Kg
Example:- for 20 m3 volume of concrete.

a) Quantity of cement required = (1:2:4)
=1/(1+2+4) x 1.52 × 20 = 4.14m3 x 1440/50 =119.26 bags

b)Quantity of Sand required = (1:2:4)
=2/(1+2+4)×1.52x20=8.28m3 OR =4.14 x 2=8.28 m3.

c)Quantity of course aggregate = (1:2:4)
=4/(1:2;4) x 1.52 x20 = 16.56m3 OR =4.14 x 4= 16.56m3.

If qty. calculate in Kg just multiply by its Sp. wt of sand
or aggregate.

Is This Answer Correct ?    68 Yes 28 No

Post New Answer

More Civil Engineering Interview Questions

Why joints are provided?

0 Answers  


what if i want to lap a 20mm dia and a 16mm dia together wat will be the lap length?? a) 1m b) 80mm

5 Answers  


how can change 12mmdia@150c/c bar spacing to 16mmdia

2 Answers   Apex,


How much steel required in 1 square feet slab?

12 Answers   Kalika Steel,


component parts of a weir

4 Answers   Infosys, L&T, Zamil Steel,






why the cracks occurs in NP3 class Hume Pipe ? And what is bearing capacity of it?

0 Answers  


What are the disadvantages while using stone dust as filler in pavements?

0 Answers  


the magnitude of the buoyant force can be determine by newtons law of viscosity archimidies principal principles of momemnt none

0 Answers  


what are the cube & Sylinder strength of concret M20,M25,M30,M35,M40,M60 ,M75,M10 ,M15

0 Answers   ABV,


what is scour depth $ what's the process to determine it?

2 Answers  


How many required steel of 1m3 slab casting?

3 Answers  


i am completed my b.tech EEE in 2009,,,iam trying the job 3+ for AUTO CAD (ELECTRICAL),, what is the market for autocad electrical in hyderabad... how to handle the intervws give some suggestions ?

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)