Concrete Mix Design is the name of procedure...it can be performed by BIS or ASTM standerds.
things to be known/assumed:-
1.compressive strength of 28days
2.maximum size and type of aggegate
3.degree of qulity of controll,workability and
4. type of exposure/type of cement etc
procedure:-
1. find target mean strength-by Ft=Fck+1.65*s(s-std deviation ,varries w.r.t grade of conc.)
2. water cement ratio- this find with the help of a graph W/C ratio Vs Fck.approximate air contant s found by another table wrt aggre gates s max size.(genrally-0.6to .35)
3.find workabiliti den multiply by 0.8follow a table to find zone nd % of sand .
4.now cement ,voids sand water are known along with total aggregate then finally using a specific formula given in BIS course and fine aggregates r also estimated.
| Is This Answer Correct ? | 1 Yes | 10 No |
Post New Answer View All Answers
16 questions out of 55 were from the book GUPTA N GUPTA OBJECTIVE of civil engineering. Total ques were 4 ques from hydraullics, 7 from BMC, 4 FROM SOM, 4 from soil mechanics, 6 from transportation, 5 from engineering drawing.
What is Rankine Cycle?
How to get MEP technical,instaaltion & testing data for interview?
strength vs shape factor
material used for mendrel use to bend epoxy coated rebar
Define line type?
What is the ratio of grades m5, m7.5, m10, m15, m20, m25, m30, m35, m40?
How to calculate the quantity of ingredients of M20 grade concrete?
How much quantity of cement and sand required for the inlining of 610mm dia MS pipe 8.7mm thk.Inlining thickness is 10mm and CM ratio is 1:1.5.
i am completed my b.tech EEE in 2009,,,iam trying the job 3+ for AUTO CAD (ELECTRICAL),, what is the market for autocad electrical in hyderabad... how to handle the intervws give some suggestions ?
HOW MUCH STEEL REQUIRED FOR SLAB OF AREA 23'3"*18.3"? FOR SLAB HOW MUCH DIAMETER BAR WILL USE?
what is the hanekom repairing material after concreting work
detailed calculation of the amount of cement used?
Laying bitumen concrete 40mm thick using 0.1372 cum of 13.2 10mm metal ,0.2387 cum of 10 5mm metal...what did it means please explain me how much cum of 10 mm metal need?
On what basis we decide the formation level of the road? other then that of 50% Cutting and 50% Filling??