ACCOUNTING AND FINANCIAL ENGINEERING - EXAMPLE 34.31 : In a biochemical engineering company, let the actual revenue generated = A, actual cost incurred = B. According to the standard budget, the revenue generated = C, cost incurred = D. (a) Find the profit according to : (i) actual situation; (ii) standard budget. (b) Calculate the Variance Due to Price and Efficiency in : (i) revenue generated; (ii) cost incurred; (iii) profit. (c) If E > F where > represents : more than, find the 4 pairs of values of E and F in favorable conditions.
ACCOUNTING AND FINANCIAL ENGINEERING - ANSWER 34.31 : (a)(i) actual profit = A - B; (ii) budgeted profit = C - D; (b)(i) revenue variance = A - C or C - A; (ii) cost variance = B - D or D - B; (iii) profit variance = (A - B) - (C - D) = A + D - B - C or (C - D) - (A - B) = C + B - D - A. (c) Favorable conditions will generate more profits according to actual situation, then A > B, C > D, A > C, D > B. The paired values of E - F are : A - B, C - D, A - C, D - B. The answer is given by Kang Chuen Tat; PO Box 6263, Dandenong, Victoria VIC 3175, Australia; SMS +61405421706; chuentat@hotmail.com; http://kangchuentat.wordpress.com.
| Is This Answer Correct ? | 0 Yes | 0 No |
At what temperature does water have maximum density?
Explain what are the criteria involved in choosing mass balances for components?
Define an additive?
1.How a chlorine leak is detected? 2.What would happen if excess chlorine is added to water in cooling tower?
CHEMICAL FLUID MECHANIC - EXAMPLE 3.1 : Water flows through a pipe with circular cross sectional area at the rate of V / t = 80 L / s where V is the volume and t is time. Let Av = 80 L / s where A is cross sectional area and v is velocity of fluid. For point 1, the radius of the pipe is 16 cm. For point 2, the radius of the pipe is 8 cm. Find (a) the velocity at point 1; (b) the velocity at point 2; (c) the pressure at point 2 by using Bernoulli's equation where P + Rgy + 0.5 RV = constant. P is the pressure, R = density of fluid, V = square of fluid's velocity, g = gravitational constant of 9.81 N / kg and y = 2 m = difference of height at 2 points. The pressure of point 1 is 180 kPa.
What factors go into designing the vapor space of kettle type reboiler?
whats the allowed tolerance of pipe to pipe butt joint mismatching
diffirance between heat transfer & thermodynamics
3 Answers Shinsung Petrochemicals,
NATURAL GAS ENGINEERING - QUESTION 26.2 : (a) The Hyperion sewage plant in Los Angeles burns 8 million cubic feet of natural gas per day to generate power in United States of America. If 1 metre = 3.28084 feet, then how many cubic metres of such gas is burnt per hour? (b) A reservoir of natural gas produces 50 mole % methane and 50 mole % ethane. At zero degree Celsius and one atmosphere, the density of methane gas is 0.716 g / L and the density of ethane gas is 1.3562 mg / (cubic cm). The molar mass of methane is 16.04 g / mol and molar mass of ethane is 30.07 g / mol. (i) Find the mass % of methane and ethane in the natural gas. (ii) Find the average density of the natural gas mixture in the reservoir at zero degree Celsius and one atmosphere, by assuming that the gases are ideal where final volume of the gas mixture is the sum of volume of the individual gases at constant temperature and pressure. (iii) Find the average density of the natural gas mixture in the reservoir at zero degree Celsius and one atmosphere, by assuming that the final mass of the gas mixture is the sum of mass of the individual gases. Assume the gases are ideal where mole % = volume % at constant pressure and temperature.
Why do we apply on iron articles?
ACCOUNTING AND FINANCIAL ENGINEERING - EXAMPLE 34.28 : In the development of a small engineering facility for biochemical processing, completed contract method is applied in its construction accounting. In a short contract period, let the (contract price) = A. Let the (costs to date) = B; (estimated cost to complete) = C. (a) Find the values of : (i) estimated total costs; (ii) total estimated profit; (iii) percent completion to date. (b) If the project contract is 100 % completed : (i) find the total gross profit recognized; (ii) what is the exact numerical value of C?
have any one question paper of institute of plasma research center for aptitute as well as technical?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)