Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


what is the use of dowels rod..?

Answers were Sorted based on User's Feedback



what is the use of dowels rod..?..

Answer / vikas

MIN.12 MMDIA

Is This Answer Correct ?    0 Yes 0 No

what is the use of dowels rod..?..

Answer / nitin adate

Dowel is just a lapping to the reinforcement which is delibrately kept to cast the adjacent structure afterwards due to site condition. The length is given by consultant.

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

Who designed the city of washington dc?

0 Answers  


cement quantity in 1 M3 pcc

2 Answers  


How do you calculate the surface area of the paver blocks, in oreder to find out the compressive strength of the same ?? And which codes are used for testing of paver blocks ?

1 Answers   BP Sangle Constructions, ECMAS,


How many litres of water used for curing of 1000sqft of slav

0 Answers  


which type of instrument included in plumbing work?name of instrument?

0 Answers   Gammon,


how statics is different from dynamics

0 Answers  


Which one is the main bar in a square slab (2m x 2m)

7 Answers  


08. 4 main points about check list for Shuttering works are––– 4 i) ii) iii) iv) 09. 4 main points about check list for Concreting works are––– 4 i) ii) iii) iv) 10. 4 main points about check list for Plaster works are––– 4 i) ii) iii) iv) 11. 4 main points about check list for Brick works are–– – 4 i) ii) iii) iv) 12. 3 main points about Project delaying factors are––– 3 i) ii) iii) 13. Write down 60-grade M.S. deformed bar specification. 3 14. 3000 psi concrete means: 1 15. 4 main points about methods of wastage control are–– – 4 i) ii) iii) iv) 16. 1 main point about reasons for your honesty is : 1 17. Water cement mixing in hopper less mixture machine is better than hopper mixture machine because: 1 18. 2 main points about your role during roof casting are–––– 2 i) ii) 19. a. The weight of 3333m deform bar of 24.5 mm dia is…… 1 b. The weight of 300 rft plain bar of dia 1&#61618; is……. 1 20. The types of slumps are––– 3 i) ii) iii) 21. 4 main points about the causes of cylinder failure are––– 2 i) ii) iii) iv) 22. Detection of a beam & a girder are–––– 2 i) ii) 23. Curing is needed for–––– 1 24. The types of slabs in respect of size & shape are––– 5 In respect of size: i) ii) In respect of Shape i) ii) iii) 25. The types of Column in respect of size & shape are–– – 9 In respect of size: i) ii) In respect of Shape: i) ii) iii) iv) v) vi) vii) 26. 3 field tests & 3 Laboratory tests of bricks are––– 6 Field tests: i) ii) iii) Lab test: i) ii) iii) 27. 2 field tests & 1 Laboratory tests of sand are––– 3 Field tests: i) ii) Lab test: i) 28. 1 field tests & 1 Laboratory tests of M.S rod are––– 2 Field tests: i) Lab test: i) 29. a. The % of water absorbs by brick chips: …………… 1 b. The % of water absorbs by Stone chips: …………… 1 30. In respect of design: 5 a. The % of strength gains by concrete in 28 days= b. The % of strength gains by concrete in 14 days= c. The % of strength gains by concrete in 07 days= d. The % of strength gains by concrete in 03 days= e. The % of strength gains by concrete in 28 days without curing =

3 Answers  


how to convert udl into point load??

1 Answers  


what values & beliefs have guided you in your career path

0 Answers   IVRCL,


what type of waterproofing and procedure using in building?

1 Answers   Tulip,


WHAT IS THE SPLICE LENGTH WHEN WELD IN REINFORCEMENT STEEL

8 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)