how much quantity of water is required for main wall brick work, partition wall brick work,and for internal and external plastering and how it is calculated?
Answer / vinay
if they give the give w/c ratio then we can calculate water quantity.
for eg if 0.3 is the w/c ratio then,
w/c=0.3
then 1 bag of cement contains 1.25cft so, 0.3*1.25= 0.375cft
1cft contains 28.34 litrs of water then 0.375*28.34=10.625 litres of water is required for 1 bag of cement, generally here for dry volume of concrete is taken as 1 and half times the wet volume i.e 1.54
| Is This Answer Correct ? | 1 Yes | 0 No |
which grade of cement mostly used in construction and why..??
what are the tests conducted on cement,aggregate and concrete?briefly explain that tests procedure and limits adopted for safety side.
What happens to Load at yielding ?
What is indicate Fe250 in steel structure?
cause of cylinder test failure
which has high compressive strength between hollow block and brick masonry?
What is green building?
How to calculate labor requirement or requirement of labor projction for a proposed multistoried building for which quantities of different items of work has been already calculated stage wise ?
limit value of bulking of sand
the volume of cement req for 70cum of brickwork in 1:6 cement mortar is approx is equal to 3cum 5cum 7cum 1ocum
What is the acceptable percentage of slump in Mix concrete?
what should be the deduction for bend in stirrups while calculating cutting length? Is it 1 dia at each bend?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)