how much quantity of water is required for main wall brick work, partition wall brick work,and for internal and external plastering and how it is calculated?
Answer / vinay
if they give the give w/c ratio then we can calculate water quantity.
for eg if 0.3 is the w/c ratio then,
w/c=0.3
then 1 bag of cement contains 1.25cft so, 0.3*1.25= 0.375cft
1cft contains 28.34 litrs of water then 0.375*28.34=10.625 litres of water is required for 1 bag of cement, generally here for dry volume of concrete is taken as 1 and half times the wet volume i.e 1.54
| Is This Answer Correct ? | 1 Yes | 0 No |
why building got air crack? if it get in one particular are what is means?
logical reasoning
Dear sir, i want to NBCC & NTPC previous exam papers email Id : madhu_bingi@yahoo.co.in
what"s the formula to find the cement,sand,aggreegate(45mm) requirement for PCC?
How to find the concrete volume in sloped footing??? illustrate with example
define the authorized overlap in columns
What is the percentage of wastage in cement n how to control it?
What does civil status mean?
why elongation index is not required for concreteing coarse aggregate..
How is calculate the cube molt
in the earthquqke the profile of water on dam is parabolic or not
how to design paver block
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)