what is difference between design mix and nominal mix,where the design mix is used?

Answers were Sorted based on User's Feedback



what is difference between design mix and nominal mix,where the design mix is used?..

Answer / menaka

We can say some proportions up to M20 which is called nominal mix..beyond this like M30,M40 we can't define this proportions of cement and aggregates roughly without designing ..it should be designed on the basis of properties of material in such cases..it's called design mix

Is This Answer Correct ?    1 Yes 0 No

what is difference between design mix and nominal mix,where the design mix is used?..

Answer / srikanth

M20 is the Nominal mix.It is used in the common slab which have design for the Low Load. 
M25 is the Design mix.It is used for the Design slab for the required compressive strength for the Design load Obtain.  

Is This Answer Correct ?    2 Yes 2 No

Post New Answer

More Civil Engineering Interview Questions

which is cost effective Steel Structural or Concrete Structure building?

3 Answers  


what is the crushing strength of stone and bricks?

2 Answers   DFCCIL, FWO, Habib Group, HBL, KPSC Kerala Public Service Commission, Mott MacDonald,


A doubly reinforced concrete beam is 25 cm wide and 50cm deep to the centre of tension reinforcement. The centre of compression is steel is 5cm from the compression edge. The areas of the compression and the tension steel are 10.16cm2 and 12.56 cm2 if m=18 and the bending moment at the section is 7,000,000 N-cm. Calculate the stress in concrete and steel.

0 Answers  


how many shuttering material required for 1000 sq.m built up area.

0 Answers   ABC, CGHB,


what"s the responsibilities for QC(quality controler)in high rise buildings?

5 Answers   Ashok Leyland,






design mix for M15,M20, M25,M30 please

2 Answers   CIDC, Design Ideas,


Formula for calculation volume of essentric footing

0 Answers  


how to explain soil classification

1 Answers  


reinforcement lapping for short pile and long pile

3 Answers  


whike making bbs we deduct 2d for every bend in bar but theoretically we cant subtract 2d for every bend and for every dia of bar , so plz tell me the exact deduction for bends for different dia of bars and for different angles ??

1 Answers   Sobha Developers,


what will be the cost of constructing a plinth of (40x40x4)ft and a PCC layer of 4 inches?

4 Answers  


pls explain me the design procedure of multistorey building including structural analysis and also with example by considering the effect of wind load and earthquake load ?

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)