How many cement mortor dry quantity required for 1m3 ?(1:4)
Answers were Sorted based on User's Feedback
Answer / pavan
total quantity required would be 1.57 cum of dry mortar,
including 20% wastage.
Dry volume of mortar is 30% more than wet volume.
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / rehaan khan
For rcc work it will 1'57 cum
For brick masonary '30cum
For plaster work it will 1'60cum..
| Is This Answer Correct ? | 0 Yes | 0 No |
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting?
WHAT ARE TYPES OF STRUCTURES
How to calculate brick work quantity?? Block work quantity??
y we need to take 28 days strength as compressive strength ? y cant we take 30 th day
how to calculate the no. of brick (18'*9'-wall)
how to calculate concrete qty for footing using M25 grade 1:1:2 for 731 cft.
9 Answers Abuilding Lab, L&T, MPSC, Vellapally,
What is the standard size of a brick used in North India?
is excessive curing for brick work is good or bad for the walls?
Can we use Polystyrene as a Bitumen modifier !! if so is it a good MS research topic ? and what type of laboratory tests will be conducted during Research work ??
How much cost will come for 900 sq ft cement plastering
how to calculate the amount of cement & sand required for plastering
WHAT IS IS CODE FOR USE TOR & TMT STEEL
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)