Used Cement Mortar, Cement & Sand in 1 Square Meter or 1
Square Feet For 10-18mm Thick Plaster ? (1:6) (1:4)(1:3)

Answers were Sorted based on User's Feedback



Used Cement Mortar, Cement & Sand in 1 Square Meter or 1 Square Feet For 10-18mm Thick Plaster..

Answer / gulshan vashisht

CementMorter 1;4

Is This Answer Correct ?    6 Yes 1 No

Used Cement Mortar, Cement & Sand in 1 Square Meter or 1 Square Feet For 10-18mm Thick Plaster..

Answer / uttam sasavade

If 1:4 Plaster Qty for 100 M2
= Wet Volume of Material 100 m2 x 0.018= 1.80 m3
= Dry Volume consider 25 % extra= 1.80 m3 x 1.25 = 2.25 m3
required.

1/5 =0.200 * 1.25= 0.25 / 0.0347bag= 7.204 bag req. for 1 m3

Cement required for 2.25 m3 x 7.204 bag= 16.209 bag.
Qty. required for 1 m2= 16.206 /100 = 0.16 bag
Sand 4/5= 0.8 * 1.25= 1 m3 x 2.25 m3 =2.25 m3 /100

sand Required for 1 m2 plaster 0.0225 M3

Is This Answer Correct ?    4 Yes 2 No

Used Cement Mortar, Cement & Sand in 1 Square Meter or 1 Square Feet For 10-18mm Thick Plaster..

Answer / umesh

1:4

Is This Answer Correct ?    2 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

Strength of brick?

2 Answers   YSB,


Can we use concrete of slump cone in cube casting in which we have already measured slump?

0 Answers  


what is the length of a steel bar when it buy for the site????

4 Answers  


9*9 1:4:8 ratio using for p cc work please tell quantity 40mm aggregate ,sand &cement

8 Answers   L&T,


which type of cement is used for RCC construction?Why?

4 Answers  






The mixture of different ingredients of cement is burnt at?

0 Answers  


how much brick,cement,and sand required in 1cum brickwork(1:4)

8 Answers   JMC, RK,


How to calculate Rate of 10 cum of Brick masonary,if the rate of material are as fallow? sand=Rs.500/mt Brick=Rs.5/brick Labour=Rs 300/day Free issue=cement+water+electicity.

2 Answers  


pl.may i place dry mix in casting of drain bed partialy filled with water?if no pl explain.

3 Answers   KMC,


show answer/calculate mix 1:2:4 ratio -cement-sand -metal-water

0 Answers  


What are the methods to do a estimate.

3 Answers   Jindal, L&T, Soba,


plz send me civil q papers of hpcl

5 Answers   Shell,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5084)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16631)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1094)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)