Used Cement Mortar, Cement & Sand in 1 Square Meter or 1
Square Feet For 10-18mm Thick Plaster ? (1:6) (1:4)(1:3)
Answers were Sorted based on User's Feedback
Answer / uttam sasavade
If 1:4 Plaster Qty for 100 M2
= Wet Volume of Material 100 m2 x 0.018= 1.80 m3
= Dry Volume consider 25 % extra= 1.80 m3 x 1.25 = 2.25 m3
required.
1/5 =0.200 * 1.25= 0.25 / 0.0347bag= 7.204 bag req. for 1 m3
Cement required for 2.25 m3 x 7.204 bag= 16.209 bag.
Qty. required for 1 m2= 16.206 /100 = 0.16 bag
Sand 4/5= 0.8 * 1.25= 1 m3 x 2.25 m3 =2.25 m3 /100
sand Required for 1 m2 plaster 0.0225 M3
Is This Answer Correct ? | 4 Yes | 2 No |
Strength of brick?
Can we use concrete of slump cone in cube casting in which we have already measured slump?
what is the length of a steel bar when it buy for the site????
9*9 1:4:8 ratio using for p cc work please tell quantity 40mm aggregate ,sand &cement
which type of cement is used for RCC construction?Why?
The mixture of different ingredients of cement is burnt at?
how much brick,cement,and sand required in 1cum brickwork(1:4)
How to calculate Rate of 10 cum of Brick masonary,if the rate of material are as fallow? sand=Rs.500/mt Brick=Rs.5/brick Labour=Rs 300/day Free issue=cement+water+electicity.
pl.may i place dry mix in casting of drain bed partialy filled with water?if no pl explain.
show answer/calculate mix 1:2:4 ratio -cement-sand -metal-water
What are the methods to do a estimate.
plz send me civil q papers of hpcl