Used Cement Mortar, Cement & Sand in 1 Square Meter or 1
Square Feet For 10-18mm Thick Plaster ? (1:6) (1:4)(1:3)
Answer Posted / uttam sasavade
If 1:4 Plaster Qty for 100 M2
= Wet Volume of Material 100 m2 x 0.018= 1.80 m3
= Dry Volume consider 25 % extra= 1.80 m3 x 1.25 = 2.25 m3
required.
1/5 =0.200 * 1.25= 0.25 / 0.0347bag= 7.204 bag req. for 1 m3
Cement required for 2.25 m3 x 7.204 bag= 16.209 bag.
Qty. required for 1 m2= 16.206 /100 = 0.16 bag
Sand 4/5= 0.8 * 1.25= 1 m3 x 2.25 m3 =2.25 m3 /100
sand Required for 1 m2 plaster 0.0225 M3
| Is This Answer Correct ? | 4 Yes | 2 No |
Post New Answer View All Answers
five benefits of using standard terminology in the measurement process
what is flexible and rigid footing?
Suppose you planning to paint newly fabricated workshop building made of structural steel of 10 tons total mass. How many litters paint primer for 1 coat and 2 coat of top coat?
how to balance aggregate during mix design of concrete???? how to calculate moisture content like C/A,F/A and how many percentage using ice instead of water for example of we are preparing ice concrete??????
why we create short columns under grade slab?
please give the detail design for the soring and shuttering for 8.5m deep excavation in the sandy soil for 25x10 rectangular streaches
what is the breaking strength of wall tiles
Mention different types of roof systems?
CAN WORK WELL UNDER DEAD LINES OR PRESSURE?
what is meant by residual strain?
What are segregation and bleeding?
Define polar co ordinates.
In a beam,stirrups are placed closely at ends than at centre due to shear.similarly where would ties be closer to each other-at center or at ends in a column and slab.
what is difference between fluidity and workability also how palsticizer works
why should we use 20mm graded metal only in vrcc?why we shouldnot use 40mm metal?