Used Cement Mortar, Cement & Sand in 1 Square Meter or 1
Square Feet For 10-18mm Thick Plaster ? (1:6) (1:4)(1:3)
Answer Posted / uttam sasavade
If 1:4 Plaster Qty for 100 M2
= Wet Volume of Material 100 m2 x 0.018= 1.80 m3
= Dry Volume consider 25 % extra= 1.80 m3 x 1.25 = 2.25 m3
required.
1/5 =0.200 * 1.25= 0.25 / 0.0347bag= 7.204 bag req. for 1 m3
Cement required for 2.25 m3 x 7.204 bag= 16.209 bag.
Qty. required for 1 m2= 16.206 /100 = 0.16 bag
Sand 4/5= 0.8 * 1.25= 1 m3 x 2.25 m3 =2.25 m3 /100
sand Required for 1 m2 plaster 0.0225 M3
| Is This Answer Correct ? | 4 Yes | 2 No |
Post New Answer View All Answers
What will you do if a portion of load bearing wall collapses under your supervision?
How to calculate the load of partion in flat slab if we use brick?
hi guys what happens if you are absent for a supplymentry exam?
How to plan a project
I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
why we use aggregate,sand with cement in concrete?
why development length = 50D . why not 100D
What is the exception critarea of cube?
column at edge of a framed structure is uniaxial or biaxial. and is an interior column is biaxial
what is the mix design for M:60 with micro silica andmetakaoline?
what is the weight of 12mm aggregates?
what r you reqired for concrete baching plant?
a sewer which receives the discharge of no. of house sewer is called house sewer lateral sewer intrcepting sewer sub-main sewer
sir I got selected in rail vikas nigam limited and they call for interview but i don't what they will ask in interview please guide me if you have any experience
Define What is a kip?