Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


Require Generator Capcity ( KVA ) for 3 Phase Motor having
4.7Kw with starting current of 16amps?



Require Generator Capcity ( KVA ) for 3 Phase Motor having 4.7Kw with starting current of 16amps?..

Answer / asif.k64@hotmail.com

KW=KVA*P.F
4.7=KVA*0.8
KVA= 6KVA approx

However the starting current is 16A hence we require a DG
of higher capacity.

This can be achieved by using a 7KVA DG.

Is This Answer Correct ?    5 Yes 1 No

Post New Answer

More Electrical Engineering Interview Questions

what is phase to phase fault? what is line to line fault?

6 Answers  


for a slip ring induction motor if the stator is short circuited and rotor is given supply? how does the rotor rotate?

1 Answers   TNEB Tamil Nadu Electricity Board,


why connecting surge unit in contactor coil

0 Answers  


How electrical power is generated by an A.C Generator ?

1 Answers   Hindalco,


Why does the Solid state Rectifiers for 3-ph brake motors sometimes have 2 & sometimes 3 output terminals?

0 Answers  


rrb question

0 Answers  


I want to put this query to SENIOR & EXPERIENCED ELECTRICAL ENGINEERS. 1)I want to know about the control circuit diagrams for control panels. I found it difficult to understand. Is there ant booklet through which we can learn the circuit diagrams? 2)I want to learn about conduiting, laying cables, preparing cable schedules and various techniques which is the part of building infrastucture(construction field). I don't have any experience in this area. I have experience in control panels only. that's why i am not getting any opening in building infrastucture (construction field).Can I get the job in this field as Trainee Engineer? How to enter this field? I need job in PUNE

0 Answers  


What are the raitings of Mcb,mccb and Acb in detail ??

0 Answers   Engineering Vision,


What is the lifetime of a Thyristor? Is there a recommended lifetime for thyristors after which they should be replaced?

0 Answers  


800a siemens vcb in our company can not be closed electrcally an mechanicaly cc and oc coils are found ok. why?

2 Answers  


what is HVDC, what are advantages over conventional system?

1 Answers  


Give me clear explanation.What is the Different Between Load break switch and Vacuum circuit breaker

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)