what is the procedure for erection of a transformer



what is the procedure for erection of a transformer..

Answer / debasis sahoo

During installation of Transformer on a Pole mounting structure, following checks should be made:
Ensure that the base channel of transformer is at height complying to IEC Standards:
a) Height of top of HV bushing from ground for pole mounted transformer should be 4.572 meters minimum (15 Ft)
b) Height of top of HV bushing from ground for plinth mounted transformer should be 2.75 meters minimum (8 Ft)

Ensure that base channel is horizontally leveled

Avoid jerky movement of the transformer while lifting it upwards during installation

During installation ensure that the HV bushings of the transformer are on the DO unit (or HG fuse unit) side of the structure

After installation of transformer, also check that other allied equipments such as AB switch, Horn Gap fuse units, DO Fuse sets, Lightening arrestor etc. are fitted at appropriate positions as per the applicable drawing issued by the utility.

Use PVC unarmoured cable (3 ½ core) of appropriate size and length for LV side. Ensure that the lugs are appropriately crimped at the ends.

Is This Answer Correct ?    2 Yes 0 No

Post New Answer

More Electrical Engineering Interview Questions

In 110V DC supply,if a closed circuit gets open, How can we identify the voltage which is measured after the resistor(4KOhm) which is open with negative.it shows 55V +ve when measured, also the actual positive source is 55V +ve .Because there is no voltage drop in open circuit. How can we identify whether this is the voltage which is series with the resistor or the DC source direct +ve.

1 Answers   GE,


What is the difference between power,voltage,current? and with example

3 Answers  


What is the meaning of BREAKING and MAKING CAPACITY in case of CIRCUIT BREAKERS.

2 Answers  


what will happen if dc machine are supplied by ac source??

2 Answers  


Do you know the faults occurs generally in motors and how to rectify them?

4 Answers  






how to calclate fault level

2 Answers  


What is the name of process In VFD frequency are increase then voltage increase & frequency decrease then voltage decrease?

0 Answers  


% voltage variation in distribution a)1% b)5% c)10% d)15%

2 Answers  


what is relation between vector group of transformer and its load hormonics?

1 Answers   Sanmar,


what is the difference between isolation and insolation ? please explain in detail with example.

5 Answers   ABB,


how do you tell if a avalanche button diode is a p or an

1 Answers  


i completed my DEEE. and i want to electrical c license. how to get it..?

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)