Difference between overlap and development length of rod.
Thanks.
Answers were Sorted based on User's Feedback
Answer / santosh singh
1) overlap= during placing steel for RCC structure if the
required length of bar is not available then lapping ie.
placing two bars side by side for a designed length is done.
lap length is in between 40d to 60d where d= diameter of
the bar. but if overlap length is not given 50d value is
assumed
eg, if dia of bar is 12mm then
lap length= 50x 12 = 600mm
2)Development length= (nominal diameter of bar x stress in
bar) / (4 x design bond stress )
if d=12 mm
stress in bar =415 N/mm2
design bond stress for M20 CONCRETE = 1.2 N/mm2
then,
Ld = 12 x 415 /4 x 1.2 = 1037mm say 1m
this length is for steel in tension while development
length for steel in compression is 25 % less
ie in compression zone development length for same detail
will be = 1- 25/100x1= 1-.25 =0.75m ie 750mm
| Is This Answer Correct ? | 97 Yes | 10 No |
Answer / madhukeshwara`
d=16 mm for compression steel
stress in bar =0.87 times of 415 N/mm2 = 361.05N/mm2
design bond stress for M20 CONCRETE = 1.2 N/mm2
then,
Ld = 16 x 361.05 /4 x 1.6X 1.2 = 752.02 mm
d=16 mm for tension steel
stress in bar =0.87 times of 415 N/mm2 = 361.05N/mm2
design bond stress for M20 CONCRETE = 1.2 N/mm2
then,
Ld = 16 x 361.05 /4 x 1.25X 1.2 = 962.8 mm
| Is This Answer Correct ? | 21 Yes | 7 No |
What is the calculation for finding cement and sand for 10' * 12' area ratio 1:6 thickness 12 mm
what is difference between open and well foundation ?
how do you calculate the length of "L" of main & distribution bar for reinforcing of raft footing
how much tempareture are required to make liquid state of pid leed
As a site engineer what do you check in foundation before concreting
What is the diameter of the 3"inch nails?
how did find the quantity of cement ,sand , and aggregate in concreat which is givan by volume
Journal entry Gross salary 10000 Tax 1000 Employee contribution 2000 Employer contribution 2000
Define What does civil status mean?
In case of concrete cube test were all three molds are attached together do you cast your cubes simultaneously at the three molds every 50 mm or one after the other?
Suggest how many column, beem, etc required for 30 mtrs x 21 mtrs width x 8mtrs height for industrial shed of ground floor. I want to know the quantity of tmt steel consumption and Concrete consumption for budgeting
0 Answers Vishal Pipeline And Engineering,
how to calculate column load bearing? how many weight capacity in 1m3 concrete? pls answere me sir.
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)