Answer Posted / karunakaran
For Beams sides only 1 day
For coloumns 1 day
For slabs span<4.50m 7 days
For slabs span>4.50m 14 days
| Is This Answer Correct ? | 14 Yes | 0 No |
Post New Answer View All Answers
I want some common questions which have been asked in interviews of NTPC Limited,Satluj Jal Vidyut Nigam Ltd.,and Bharat Heavy Electricals Ltd.
it is a corrected question." make a list of engineering property(properties) of soil.
How is the leaning tower of pisa supported?
cement, sand, aggregate,reinforcement & concrete consumption per square feet in multi storeyed building
what's the formula for calculate pcc for matt(45mm aggregate)?
how to calculate the scour depth
how gradation of aggregates effect on slump of fresh concrete?
what is mc arther pile?
Can we use the flyash bricks in brick bat coba?
In tower foundation, on the time of 3 mtr pit RCC casting if water and mud is their surface of PCC then what will be do?
why the openings of sieves are square io size?
How we calculate the service time of buildings
how much cement sand n bricks required in im3?and how much in plaster?
What Are The Different Type Of Slump Test Indications?
What are the uses of groynes?