When the Internal Requisition will get generate if I define
an OSP operation in sequence 30. 10 & 20 will be other than
OSP operations.

Answers were Sorted based on User's Feedback



When the Internal Requisition will get generate if I define an OSP operation in sequence 30. 10 &am..

Answer / shabbir

The purchase requisition (PR) gets generated for OSP and not
the internal requisition.

And it depends on the Requisition Creation Time
parameter in WIP Parameters 'Outside Processing' Tab.
1. At Job/Schedule Release - The PR gets generated
immediately after the Job or Schedule is released.
2. At Operation - The PR gets generated once the move
transaction reach the Queue of the OSP operation sequence.
3. Manual - PR need to be generated manually.

Is This Answer Correct ?    19 Yes 0 No

When the Internal Requisition will get generate if I define an OSP operation in sequence 30. 10 &am..

Answer / santhosh kumar gp

It all depends on how u set the Requisition Creation Time
parameter in WIP Parameters' Outside Processing Tab.
1. At Job/ Schedule Release
2. At Operation
3. Manual

Is This Answer Correct ?    16 Yes 1 No

Post New Answer

More Oracle Apps Manufacturing Interview Questions

What all diffrent type of supply type are three and what are there use?

4 Answers  


What setups are done in WIP?

5 Answers   Satyam,


I want to create item in Inv org, why it is not taking,it is taking Master organisation,why give the reason.

2 Answers   PTC,


can any one help me to resolve this error "&SEGMENT refers an invalid output DESCRIPTION for system Items" when i query an job in the MAterial Requirements user interface

1 Answers  


How Many Inventory Org can be/are there

4 Answers   Oracle,






What is an ATP and what are there rules?

2 Answers   L&T,


If i want to map a organization structure, where i hv 1 operating unit that is looking after only purchasing and payables activities, whereas another operating unit is looking after OM as well as receivables. I hv one more warehouse or say plant, where i am manufacturing & despatching the goods. Wiil it be solved by setting up purchasing at one OU and OM at another OU. Do I need to perform any additional setups? Please Suggest.

2 Answers   Cap Gemini,


hOW CAN We define bY Product in Discrete mfg

2 Answers  


What is Reorder point and Reorder quantity? and what is its significance?

5 Answers   Imperial,


What is difference between Sub inventory Transfer and Move order Transfer?

11 Answers   BirlaSoft,


Which type of BOM is not used in WIP??

1 Answers   L&T, SRD,


how to give an decimal and fraction quantity in transaction like 1.25,3.5,1.999.

3 Answers  


Categories
  • Oracle Apps Technical Interview Questions Oracle Apps Technical (547)
  • Oracle Apps Financial Interview Questions Oracle Apps Financial (793)
  • Oracle Apps Manufacturing Interview Questions Oracle Apps Manufacturing (53)
  • Oracle Apps HRMS Interview Questions Oracle Apps HRMS (169)
  • Oracle Apps CRM Interview Questions Oracle Apps CRM (9)
  • Oracle Apps SCM Interview Questions Oracle Apps SCM (141)
  • Oracle Install Base Interview Questions Oracle Install Base (62)
  • Oracle Service Contracts Interview Questions Oracle Service Contracts (101)
  • Oracle Apps AllOther Interview Questions Oracle Apps AllOther (114)