Answer / geek
You can do all of the following on the Work Order-less
Completions window:
-Complete unscheduled or scheduled assemblies to Inventory
-Return unscheduled or scheduled assemblies from Inventory
-Scrap assemblies from and return scrapped assemblies to any
operation
-Explode the assembly's bill of material and add, delete,
and change components-and review items under lot and serial
number control
-Specify lot, serial, and lot and serial information for
assemblies and components.
-Create material reservations for assemblies that are linked
to sales orders
-Replenish production kanbans
Is This Answer Correct ? | 5 Yes | 0 No |
Answer / mohan
Work order less completion in WIP helps us to complete the
job manually without creating a job.
example.
Suppose client wants to continue a job creation function in
other ERP like peoplesoft,SAP but they wants to track
inventory in Oracle apps at that we used to go for Work
order less completion.
Is This Answer Correct ? | 4 Yes | 0 No |
What is the diffrance between std job and non std job?
What is work order less Transaction in WIP?
Which type of BOM is not used in WIP??
What are step included to make a final assembly?
What is difference between Sub inventory Transfer and Move order Transfer?
What is oracle apps project planning? is it module if so what are the contents of this module? please explain.
What is Reorder point and Reorder quantity? and what is its significance?
What are the modules generally covered under Oracle Manufacturing Apps
11 Answers Al-Qahtani, Axis Solutions, Wipro,
what is differnce between Tomanufactring leadtime and total lead time and total cumulative lead time?
hOW CAN We define bY Product in Discrete mfg
how to give an decimal and fraction quantity in transaction like 1.25,3.5,1.999.
In osp cycyle i have one finished goods -FG1 Raw material - RM1 Osp Item - OSP1 Resource -Ospres01 Charge Type -PO Move I assign dept, then i created routing and bom. then i realsed job the PO requestion Generated But when i replace on another OSP ITEM - OSP2 for OSP1 having same attributes i am not getting Po requestion CAn any one help me? Thanks in advance, Raghunandana raghu.nandana@rediffmail.com