Answer / @bhi
Waterfall model comes uder SDLC while V model comes under
STLC,in waterfall model testing is done after completion of
project but in v model testing starts from first phase i.e
from requirement.In Waterfall model no correction or
changes is done and in v model after acceptance testing the
changes can be done.
| Is This Answer Correct ? | 18 Yes | 1 No |
Answer / deepak
water fall model goes in step by step means can't back to
the prevoius step...generally used in development of a
SDLC..
while V model belongs to the STLC that is a part of
SDLC .can be called verification and validation
process.before coading part at every step there will be
verification after coading at every step there will be
validation.
| Is This Answer Correct ? | 5 Yes | 1 No |
Hai...
The difference between waterfall model & V-model
1.In Waterfall Model the tester role will take place only
in the test phase but in V-Model role will take place in
the requirement phase itself
2.Waterfall madel is a fixed process u can't make any
changes in the requirement or in any phase.but in V-Model u
can make any changes in the requirements
3.V-model is the simultaneous process but it is not in case
of water fall model
4.waterfall model used only the requirements are fixed but
V-model can be used for the any type of requirement
(Uncertain requirement)
5.Waterfall model comes uder SDLC while V model comes under
STLC
6.In waterfall model testing is done after completion of
project but in V- model testing starts from first phase i.e
from requirement.
K.Byeee..
Thanks&Regards
B.Ramyasri
| Is This Answer Correct ? | 4 Yes | 0 No |
Answer / jaya
In case of Waterfall model The phases are implemented sequentially while in the case of v model phases will be implemented paralley.
In case of water fall model user requriements does not change but not the case in V model(we can change the requriments)
In case of water fall model testing will be performed after the coding completion only .while in the case of V model coding and testing will be performed paralley due to this we can identify and verify the bugs in the earlier stage
| Is This Answer Correct ? | 1 Yes | 0 No |
This is the question related to Traceability Matrix. Say we have 10 requirements for a project. If one of the testing team member misses the 9th requirement. Then how can we justify the Traceability Matrix and what is the further action to be taken. Please advice.
Preference should be given for High priority bug or Critical severity bug?
How do you prepare a regression testing suite?
how can we upload manual test cases in testdirector
Do you agree testing is needed?Justify it?
Project had been started in Manual testing and Automation of some fixed modules, Then finally decided to Test the total Application in Automation then it is possible to test that application.
What is an inspection in software testing?
suppose u got defects.we r send to this through TD.Before that where we r stored
What testing roles are standard on most testing projects? Categories: Software Testing
What are the cases why parameterization is necessary when load testing the Web server and the database server?
what tests U'll do when u r doing web testing
3 Answers BT, GL Noble Denton,
can you tell me test cases this the sketch is below here name is a dropdown list like different phones nokia,lg,samsung,motorola,sony,micromax and there is a submit button below name model submit