How do speedup the project delivery without affecting the
cost?
Answers were Sorted based on User's Feedback
Answer / k.sharief
1. Reducing Scope of the work.
2. Parallelizing non dependent activities.
3. Identify & Ensure the completion of critical activities.
4. Early identification and minimizing risks and issues.
5. Outsourcing non critical activities which can be completed
by the external agency at lower cost.
6. Continuous follow-up for the delivery of long lead time in
the procurment area.
7. Avoid rework.
8. Effective utilization of manpower (resource leveling).
9. Pay attention to planning & Schedule.
Is This Answer Correct ? | 25 Yes | 2 No |
Answer / sanjay ursal
The procedure is called Fast Tracking. Starting Sucessor
activities before the completion of their Predessor
activity.
Fast tracking is risky, needs very good coordination and
may involve rework.
This can be achieved only incase you are a different set of
resources on the predecessor and sucessor activities also
incase of any free resources u can utilize to do this.
Is This Answer Correct ? | 14 Yes | 6 No |
Answer / a
If you are working with MS project, you can identify the
resources which have lead or lag time and then allocate the
activities to idle resources.
Is This Answer Correct ? | 7 Yes | 1 No |
Answer / sp kumar
A proper co-ordination containing fast tracking & reveiwing
the activity & sub activity for project management is help
full to speed up the project delivery without affecting the
cost.
Is This Answer Correct ? | 5 Yes | 2 No |
Answer / chellaiah
1. Identify whether its under scope or not ?
2. If its with in the scope, then there is a mistake on
effort/cost estimation or in the planning.
3. Here the case.. we should delivery with in the budget or
estimated cost.
4. Revise the plan and make it strictly.
5. When you revise the plan, you will identify the resource
who is lead and lag.
6. Have meeting with the team mates and let them know the
situation and increase the work time.
7. According to ur revise plan ( allocate the idle resource
and lead resource ) start doing the work.
8. Make sure the daily review and work towards the revised
plan which you made against your requirement ( Delivery with
in the cost is the purpose).
Is This Answer Correct ? | 3 Yes | 1 No |
Answer / sgr
1. involving appropriate stakeholders at right time and right place.
2. involving user during baseling
3. concurrent engg.
4. Motivation
5. Refining policies and procedures during lifecycle
MOST IMPORTANT OF ALL
appoint a right project manager
Is This Answer Correct ? | 1 Yes | 0 No |
What are the different inputs and outputs of the phases in SDLC ?
How do you know what you need to deliver or do in your project?
Write a function that will return the number of days in a month (not using System.DateTime)?
Explain the various activities you do (as a PL) when the project is started up.
How are the team members kept informed about the current status of the project?
How do you estimate the effort for your project? Where is the estimation procedure documented?
What and where are the policy statements for software project planning?
What are the different phases in Software life cycle
Explain dll hell?
What are the two data table in Microsoft Project 2007?
what are all the test scenarios for login passwords?(user authentication)
How do you perform impact analysis ?