How do speedup the project delivery without affecting the
cost?
Answers were Sorted based on User's Feedback
Answer / k.sharief
1. Reducing Scope of the work.
2. Parallelizing non dependent activities.
3. Identify & Ensure the completion of critical activities.
4. Early identification and minimizing risks and issues.
5. Outsourcing non critical activities which can be completed
by the external agency at lower cost.
6. Continuous follow-up for the delivery of long lead time in
the procurment area.
7. Avoid rework.
8. Effective utilization of manpower (resource leveling).
9. Pay attention to planning & Schedule.
| Is This Answer Correct ? | 25 Yes | 2 No |
Answer / sanjay ursal
The procedure is called Fast Tracking. Starting Sucessor
activities before the completion of their Predessor
activity.
Fast tracking is risky, needs very good coordination and
may involve rework.
This can be achieved only incase you are a different set of
resources on the predecessor and sucessor activities also
incase of any free resources u can utilize to do this.
| Is This Answer Correct ? | 14 Yes | 6 No |
Answer / a
If you are working with MS project, you can identify the
resources which have lead or lag time and then allocate the
activities to idle resources.
| Is This Answer Correct ? | 7 Yes | 1 No |
Answer / sp kumar
A proper co-ordination containing fast tracking & reveiwing
the activity & sub activity for project management is help
full to speed up the project delivery without affecting the
cost.
| Is This Answer Correct ? | 5 Yes | 2 No |
Answer / chellaiah
1. Identify whether its under scope or not ?
2. If its with in the scope, then there is a mistake on
effort/cost estimation or in the planning.
3. Here the case.. we should delivery with in the budget or
estimated cost.
4. Revise the plan and make it strictly.
5. When you revise the plan, you will identify the resource
who is lead and lag.
6. Have meeting with the team mates and let them know the
situation and increase the work time.
7. According to ur revise plan ( allocate the idle resource
and lead resource ) start doing the work.
8. Make sure the daily review and work towards the revised
plan which you made against your requirement ( Delivery with
in the cost is the purpose).
| Is This Answer Correct ? | 3 Yes | 1 No |
Answer / sgr
1. involving appropriate stakeholders at right time and right place.
2. involving user during baseling
3. concurrent engg.
4. Motivation
5. Refining policies and procedures during lifecycle
MOST IMPORTANT OF ALL
appoint a right project manager
| Is This Answer Correct ? | 1 Yes | 0 No |
Does XML has white spaces?
How do you know that a particular individual is the project leader (or) how do you know that you are the Project Leader?
What is your role in the current project and what kinds of responsibilities you are handling ?
8 Answers Infosys, Iron Mountain, Wipro,
Explain dll hell?
How do you track the size or changes to size of the work products in your project?
When do revise your project plan? When do you know you have to revise your project plan? Where is the plan revision frequency documented?
what is SDLC? what are the different stages in SDLC?
45 Answers Choice Solutions, College School Exams Tests, HCL, Infosys, SDLC, Soma Enterprises, Wipro,
funds flows analysis how to prepare for interview
How do speedup the project delivery without affecting the cost?
Write the InStr function. Write the test cases for this function?
Write a function that inserts an integer into a linked list in ascending order. Write the test cases for this function.
You have 3 jars. Each jar has a label on it: white, black, or white&black. You have 3 sets of marbles: white, black, and white&black. One set is stored in one jar. The labels on the jars are guaranteed to be incorrect (i.e. white will not contain white). Which jar would you choose from to give you the best chances of identifying the which set of marbles in is in which jar?