How do speedup the project delivery without affecting the
cost?
Answer Posted / sanjay ursal
The procedure is called Fast Tracking. Starting Sucessor
activities before the completion of their Predessor
activity.
Fast tracking is risky, needs very good coordination and
may involve rework.
This can be achieved only incase you are a different set of
resources on the predecessor and sucessor activities also
incase of any free resources u can utilize to do this.
| Is This Answer Correct ? | 14 Yes | 6 No |
Post New Answer View All Answers
Test the save dialog in Notepad?
Explain dll hell?
Explain the various activities you do (as a PL) when the project is started up.
How do you ensure that your project plan is available for others to see? Where will you find the plans of other projects executed (in the past or currently) in the center?
What and where are the policy statements for software project planning?
create a flow diagram up to 2 levels for hospital management
Assignment A software house got a project to automate sales/purchase department of a furniture store. The store management is clearly transferred their requirements to the software house management. There is no chance of changing the requirements afterwards. Software house management use waterfall process model to make the project. Given is the progress flow of water-fall process model In waterfall process model, the deliverable (document) produced in one phase serves as an input to the next phase. Suppose you are a project manager who is leading this project. It is decided to work and complete the project using waterfall process model approach. You are required to develop a plan in which the key task is to decide the deliverable that should be built during and after completion of each phase. Also give a description or required contents that must be included in those deliverables. You are not supposed to make the complete project. All you are required to do is to make a Project plan. In that, you need to give a set of deliverables (documents) which according to you, should be developed in each of the phase (Requirements, Designing, implementation, Testing, Maintenance). Also provide contents which should be there in each deliverable. The contents should be clear and have brief explanation. Note:: There are one folder and one file in the attached folder. The file is named as Assignment 4 write-up which is your assignment write-up. The other folder named Project deliverables is the folder in which you are required to organize and place your deliverables. Name of the document/deliverable saved in each folder should be mentioned in the file named checklist (This file is placed in the “Project deliverables” folder) For Example If you produce a deliverable named Requirement Specification (RS) in the “Requirements” phase. You need to do following tasks 1) Finalize the RS contents 2) Save the file in sub-folder named Requirements 3) Write the name of this document in the checklist file under the heading Requirements. Similarly, you need to make and save deliverables of each phase. Not all phases contain one deliverable. There must be some phases having more than one deliverables. PLEASE SIR PRIVIDE ME THE CHECK LIST FOR GIVE SENERION ? CHECKLIST ARE: 1-Requirements 2- Designing 3- Implementation 4- Testing 5- Maintenance
When you come in to the office, how do you know what you have to do during the day?
How are the team members kept informed about the current status of the project?
I want question and paper based MS Projects. Also is there any exam which microsoft conduct for Ms Project professional to issue certification?
how to tell project details in interview the project is funds flow analysis?
Write a function that inserts an integer into a linked list in ascending order. Write the test cases for this function.
Tell about yourself and job ?
Did you used crystal reports? Do you have sufficient knowledge on crystal reports?
Please, i am a final year student in nigeria and i have a project on pension fund administration and i need help in starting.