Laboratory experiments conducted in Mumbai on a particular
mix showed a
strength of 33 MP a for a fully matured concrete. Find
whether formworm
can be removed for an identical concrete placed at Jammu at
the age of 15
days when the average temperature is 60C. The stripping
stress in concrete
Answers were Sorted based on User's Feedback
Answer / buntychandwani
First thing the question is not completely and correctely
typed. The stripping stress in concrete in missing and also
how 60 deg temp will be possible in Jammu & Kashmir.
Let us connsider the Stripping stress of concrete as 25 Mpa
and average temp is 6 deg.
Now,
Maturity = Submission (time x temp)
= 15 x 24 x [6 - (11)]
= 6120 deg CH
Plowman's Constant given as A = 21 and B = 61
Se/S 15 = A + B Log10 [ M /1000]
Percentage of strength = 21 + 61 log(6120/1000)
= 68.99
The strength of Concrete at 15 days = 33 x (68.99/100)
= 22.76 Mpa
Since the strength of concrete is less than the stress
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / buntychandwani
First thing the question is not completely and correctely
typed. The stripping stress in concrete in missing and also
how 60 deg temp will be possible in Jammu & Kashmir.
Let us connsider the Stripping stress of concrete as 25 Mpa
and average temp is 6 deg.
Now,
Maturity = Submission (time x temp)
= 15 x 24 x [6 - (11)]
= 6120 deg CH
Plowman's Constant given as A = 21 and B = 61
Se/S 15 = A + B Log10 [ M /1000]
Percentage of strength = 21 + 61 log(6120/1000)
= 68.99
The strength of Concrete at 15 days = 33 x (68.99/100)
= 22.76 Mpa
Since the strength of concrete is less than the stress to
which it is likely to be subjectd while stripping the
formwork, the concrete may fail. Therefore, the formwork
cannot be removed at 15 days time.
| Is This Answer Correct ? | 1 Yes | 1 No |
what is rigid pavement
Reinforcement details at hinged joint
I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations
I got a concrete base to do 2200 x 2200 x 150 mm can you tell me how to calculate the quantity of cement to use
how to calculate the circular beam reinforcement.its a helipad beam. Dia of bar 25 mm. if its consider any elongation?
what is the basic difference between a singly reinforce section & a doubly reinforce section?
rate analysis of shuttering
How many bricks will be fit in one cubic meter, if the brick measurement is 0.20cm X0.08, If you also write down the formula for this question too.
How to find out slope footing concrete
0 Answers Ekta World, Punj Lloyd Ltd,
How to calculate the design of column by simple method?
How to calculate the wall thickness of building?
Please tell me about surveying standard chain details.Thanks.
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)