HOW DO YOU PROVE THE HIGH VOLTAGE CABLES OR BUSBAR IS DEAD
EVEN AFTER IT IS DE ENERGISED
Answers were Sorted based on User's Feedback
Answer / dhandapani muthu.r, je tneb, i
Unless otherwise it is discharged and earthed it should be
treated as energised. We have to discharge and eath that
bus or cable with a set of earth rods. Then only it is
proved. We could also use a remote sensor to prove that it
is dead.
| Is This Answer Correct ? | 13 Yes | 3 No |
Answer / rod
As we are dealing with high voltage it is critical that the
correct procedure is used. 1/ A switching sheet should be
used to ensure that both sides of the test point is
isolated locked and tagged, 2/ A Modiwak (HV sensor) should
then be tested on a known live source first then the
isolated point should be tested and the Modiwak should then
be retested on the known live source, this ensures that the
Modiwak is functional, 3/ Then dressed in the correct PPE
earths may be installed, making sure the the earths are of
a size for the fault level at that point.
All the previous answers are partly correct but to prevent
accidents it is esential that a strict procedure is used.
| Is This Answer Correct ? | 8 Yes | 0 No |
Answer / hassan
BOTH SIDES BREAKER OPENED , DE-ENERGIZED AND EARTH APPLIED.
| Is This Answer Correct ? | 7 Yes | 3 No |
Answer / giri
Nowadays we have got HT sensors which will give indication
when it is brought near the live bus bar.
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / kedar
After taking all the necessary steps to discharge the bus-bars even then u r not confirmed. Then you should use a special meter which works on induction principle which senses the magnetic field of the bus bar and will tell u whether the bus is discharged or not.
| Is This Answer Correct ? | 0 Yes | 2 No |
Answer / siddharth tayade
unless there is nothing any potential refrence to earth and
bus
| Is This Answer Correct ? | 0 Yes | 3 No |
Explain Active power,reactive power,how its related to each other , & inductive ,capacitive.
Calculate the demand in KVA for a three phase 440V power source drawing 1100A current
IR value for 30kw lt motor
what is pmg and its use
Using 11000V/433V,3 ph,50Hz,500 KVA, what is the maximum capacity of motor in KW that can be connected and started at a single moment? Also explain about any calculations and formulas used in deriving the same.
After synchronization with grid how to maintain the power factor in lagging or in leading? if lead of lag what is the problem?
what is transformer
What is the harm if we install primary side 11 KV VCB at a distance of one Km from the 11/3.3KV 12.5 MVA transformer through 11 KV cable.
how to check the continuity of a cable with a megger
how to calculate the bus-bar size. give formula with description
what is the difference between equipment earth and system earth.
how to select electronic timer(Star-Delta) setting for diff. rating motors
0 Answers Getrag Ford Transmissions,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)