form work including the props can be removed from beams only after
Answer / subhayan
depends on span for upto 6m 14 days and more than that 21days
Is This Answer Correct ? | 4 Yes | 1 No |
what is meant by concrete joints?
Lap length may different for FE 415 and FE 500 Steel, If different what is the different, In which code is mentioned
How to compute minimum number of columns required for a site from area of site?
what is the comprasive stranth of brick
from one meter cube of stone masonry structure how much cubic meter of cement mortar we use as our estimation 25-30% is that correct for estimation of quantity of sand and cement(2:1) proportion of mortar
How the reconcilation of the steel can be done?
3 Answers IL, JMC, JMC Projects, Simplex,
What is the Systematic Responsibility Site Engineer? Who are the above and under co-oridinating ? What is office & Site co-ordination of Site Engineer?
How we can calculate the quantity of sand, & cement, & also aggregate for a slab. Length 25'/3.28 = 7.62 Mtr width 20'/3.28 = 6.09 Mtr depth 6" /3.28 = 0.152 Mtr
How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.
How we can calculate cement and sand for a wall 25ft x 28ft.Thickness of wall is 9inches.
how to estimate material requirement for an area of house in square feet?
what is ph value of water