Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


Sir what reason the deshuttring of column 1 day after casting and slab deshuttring time 14 days after casting 



Sir what reason the deshuttring of column 1 day after casting and slab deshuttring time 14 days afte..

Answer / rethina kumar

generally concrete is strong in compression, weak in tension, that is reason we providing reinforcement in tension zone.

1.column is compression zone, so one day is enough to deshutter
2.slab is tension zone, so it need minimum 14 days to deshutter

Is This Answer Correct ?    30 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

how to frame the sentence in voucher pad ? Description : 1.Food Expenses during site visit 2.Stamp Paper approval expenses 3.Travelling expenses 4. sweet distribution

0 Answers   L&T, Voltas,


how to cal 1:4 in brick masonary work cement and sand?

1 Answers  


How to come 1.54 from dry to wet concrete? 

0 Answers   ASZ, L&T,


What are the benefits of rcc pipes over steel designed pipes?

0 Answers  


how to find number of 16mm bar reqired for 5m length with 125 mm spacing ?

6 Answers  


quick sand is a type of sand flow condition occuring in cohesive soil flow condition occuring in cohessionless soil all above

1 Answers  


1) what is the seewage discharge per person per day taken for design purpose as per IS codes? 2) how to convert gauge to MM like if we measure 18G as our door frame then how much is it in MM ? 3) how much binding wire is required ti tie 100kg steel ? 4) while making rings in steel reinforcement , whether the corners of rings are deducted to take out cutting length ? 5) how much carbon content should be there in steel used for construction purpose? 6) what are fe415 & fe 500 and which bars are used in general civil works?

1 Answers  


Defination of civil engineering

6 Answers  


how can we design dia of rainwater pipes ? plez explain by using formula ?

1 Answers  


Hi all, please guide me about the volume. And percentage. Of steel fibre to be used. My project. Is Sifcon.

0 Answers  


after temping in cbr mould keep how many hours mould in water

2 Answers  


if mineral admixture add into concrete then what is the differences between full cement concrete & fly ash added concrete of their SP. Gr.?and for the changes of SP. Gr. what is the changes in concrete

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)