how can we calculate cutting length of a column ring
(300 x 600)
Answers were Sorted based on User's Feedback
Answer / ejaz
SIZE OF COLUMN=400*600 mm
assume clear cover to column=40mm
Dia. of Stirrup=8mm
then
b=B-clear cover-dia. of stirrup
b=400-40-8=352mm
similarly
l=L-clear cover-dia. of stirrup
l=600-40-8=552mm
then
cutting length=2*(b+l)+2*10*dia of stirrup-5*2*dia of stirrup
cutting length=2*(352+552)+2*10*8-5*2*8
cutting length=1888mm=1.88m
| Is This Answer Correct ? | 2 Yes | 7 No |
Answer / md nahid akhtar
assume c.cover of column 30mm.
so, 2(L+B)+24D
where, D= dia of steel bar.
sol,assume dia of steel bar= 8mm
=2(540+240)+24*8
=1752mm.(cutting length for col ring)
| Is This Answer Correct ? | 10 Yes | 22 No |
Answer / animesh kulshrestha
Side cover in coulmn=40mm
If dia. of ring bar used is assumed is d= 8mm
Then,
Total Cutting length=2(L+B)-2(2x40)+2d+2(5*d)
=2(300+600)-160+16+80
=1736 mm
| Is This Answer Correct ? | 7 Yes | 19 No |
Answer / manoj mathur
Side Cover in Column=40mm
So,
L=600-2*40=520mm
B=300-2*40=220mm
If Dia. of Ring assumed d=8mm
Then Cutting Length of Ring
Cutting Length=2[(520+2*d/2)+(220+2*d/2)]+2*10d-5d
=2[(528+228]+160-40
=2[756]+120
=1512+120
=1632mm
| Is This Answer Correct ? | 3 Yes | 15 No |
Answer / tarun rajput
side cover in coloum= 40 mm
formula to calculate the cutting length =2(L+B) +20d - 5d.
=2(220+520) +20*8 -5*8
=1480+160-40
=1600mm
| Is This Answer Correct ? | 6 Yes | 18 No |
Answer / vadodara
300*600
300-80 = 220*2 = 440
600-80 = 520*2 = 1040
TOTAL
(1040+440)+(75+75) HOOK - 5(8)
=1590 mm
| Is This Answer Correct ? | 0 Yes | 12 No |
What isthe formula for square
1 Answers Panchayati Raj Department,
convert= kg into brass
How to calculate the compressive strength of 28 days of concrete where we have 7 days compressive strength?
Every Engg. know that =dia*dia/162.2 is Steel weight Formula, But very less people Know that orgin of 162.2 asumption.
3 Answers ATS, Eurotech Construction, Juniper Networks,
Method for Calculating the WEIGHT OF ANGLE ?
WAS PUMP MODEL WXB DESIGNEDIN ACCORDING API 610 STANDARD?
In an aggregate blending plant, water is sprayed before blending is performed. If the fine content in aggregate is as high as 25 %, will not the fines form into lumps / balls and distribution will not be uniform ? Further, the fines will stick onto the interior of pug mill and its content will be low. The mixed material is stockpiled for weeks / months before use. Will it not be better that blending is done in dry condition, and water will be added only during compaction at site. Please forward your comments and suggestions.
How much of the strength of concrete comes from post- production curing?
0 Answers EE Limited, Focus, Lafarge,
what post do you prefer to work in this company and why do you think you can serve better in such position?
purpose of binding wire in RCC. Structually is there any requirements that how to tie the binding wire like cross or single or how many pices combine together to bind the steel. i need structually importance of binding wire.
What are Standard weights for concete of gradeM10,M15,M20,M25,M30 Etc.
what is the average steel consumption in multy storey building as a residential and commercial?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)