where lap is provided in colom?
Answers were Sorted based on User's Feedback
Answer / fazil
As per I.S. 13920 Vertical bars of Columns shall be lapped
in regular zone (Mid-height ) only
and it should be staggered i.e. not more than 50% of bar can
be lapped at one section. In
addition to that minimum clear vertical distance between
lapped bars shall be 0.25 times lap
length.
Is This Answer Correct ? | 13 Yes | 2 No |
Answer / arunachalam subiramani
In my 20 years exp vertical member lap should be 50times dia of the bar should provided
Is This Answer Correct ? | 5 Yes | 0 No |
Answer / waseem athar
there are two types of zone in column,
1). no lap zone
2). splice zone
the lap length is provided in splice zone of column..
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / bilal ali khan
iN ZONE A That is in between
for example
colimn dimensionj all in mm
lenght=1000
breadth=300
height=2440
so we will take lenght 1000 and take it from bottom and take it from top of bottom
left space in between is 440mm it is zone a
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / waseem athar
Lap should be provided in splice zone or mid zone of column and it should be 50 times of dia of bar.
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / neelam saroj
In column Lap length should be provided at mid height only
as per IS.
and it should be staggered prperly it means not more 50% of
of bar can be lapped at one section.
=}in general practice wht i do,
lap length should be above the slab at some distace or
below the beam at certain distance.
Is This Answer Correct ? | 0 Yes | 0 No |
what are the checks to be performed while fixing a door and a window frame..at site??
what is the logical concrete mix design for M 30 Grade and the cement consumption per M3
How can i design the beam . Explain with one example
If a 12m main road straight is adjoined from both sides by 7.5 m road , how curves are given at corner for vehicle movement (measurement pls.)?
What is the density of Cement, Fly ash,20 mm aggregate, 10 mm aggregate and stone dust?
14 Answers Amrapali, Egis, Himuda, Indramas, L&T,
how to stop beam concrete between column
-what is the meaning of M.S.L for civil field? -what is the grade slab and suspension slab?
Why M15 is replaced by M20 when ammendment are made in IS456 in 2000?
diffrence between mjb & mnb
How to Know that veriation acceptable in CPWD Work Of 1:6 Cement Mortor Received Lab test report.
what is unit of density,specific gravity
Why compressive strength of only concrete cubes and cylinders tested ? why not other shapes?