Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


how many rods to be require in kg 10sq.m slab?

Answers were Sorted based on User's Feedback



how many rods to be require in kg 10sq.m slab?..

Answer / myp

It completely depends on the design given by the consultant and type of loadings, span of the slab.
The above answer is general.

Is This Answer Correct ?    26 Yes 1 No

how many rods to be require in kg 10sq.m slab?..

Answer / madhu sudhan

3.1 kg per sqm for 2 way slab

Is This Answer Correct ?    1 Yes 1 No

how many rods to be require in kg 10sq.m slab?..

Answer / darshandachchu@gmail.com

800 kgs

Is This Answer Correct ?    0 Yes 0 No

how many rods to be require in kg 10sq.m slab?..

Answer / siva

In general 60 to 80kg of rebars is required for 1 sqm of
slab. So for 10 sqm. slab, this must be multiplied and used.

Is This Answer Correct ?    2 Yes 4 No

how many rods to be require in kg 10sq.m slab?..

Answer / sugatachakraborty05

2.7 kg

Is This Answer Correct ?    6 Yes 16 No

how many rods to be require in kg 10sq.m slab?..

Answer / rajesh

8750kg

Is This Answer Correct ?    0 Yes 11 No

Post New Answer

More Civil Engineering Interview Questions

BASIC DIFFRANCE BETWEEN LIMIT STATE METHOD AND WORKING STRESS METHOD?

1 Answers  


how to cal 1:4 in brick masonary work cement and sand?

1 Answers  


Brick size ? & 1 square feet brick work for use brick

1 Answers   Ashoka Electricals,


what is the density of Coarse Aggregate in 1 cu m of Concrete?

7 Answers  


I had a plot of say 5000 sq.ft. and soil in the plot is normal soil. Now I had to work upon the tender quantities to prepare a preliminary budget within a day. Is there any thumb rule or assumptions to calculate the quantities which can differ upto 15% +/-?

2 Answers  


what is SPLICES & where it is used?????????????

3 Answers  


i am also applied for the AAI jr executive (CIVIL) written test. pls forward me the syllabus & test pattern if any question papers, any one got reply for this quaries? if ANY ONE KNOW THE DATES OF WRITTEN EXAM PLZ TOLD ME. dreamyagrawal@yahoo.com

2 Answers   AAI Airports Authority Of India,


What is point of contraflexure ?

21 Answers   Cimmco, Saveetha,


which type of foundation are most prefarable in blockcotton soils

3 Answers   IVRCL,


In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting?

0 Answers  


How to do base isolation using ETABS software?

0 Answers  


9. What have you done to improve or develop your knowledge / professional qualifications in the last year?

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)