Answer / mithilesh kumar
In Yokogawa DCS,
Domain means how much unit are present.
That means if in this plant 100mw x1 then domain
No is 1, if in this plant 100mw x 2 then domain is 2.
this communication done with the help of BCV and
CGW.
Station means how much FCS and HIS
Present for this unit. In yokogawa FCS start
With 01 and HIS start from 63.
so domain and station coding is always together.
It's symbol for eg. Is 0104.
here 01 is domain and 04 is station.
| Is This Answer Correct ? | 6 Yes | 4 No |
Answer / praven kumar m
In Yokogawa System if the no. of station is 56 or less than
56 the domain no, will be domain#1. If it exceeds more than
56 stations then we have to consider 2 domains (i.e.,
domain#1 and domain#2)
For eg. if there are 2 units, and the first unit consists
of 65 stations. in this case the first 56 stations will be
considered as domain#1 and station nos. from 57 to 65 will
be considered as domain#2. The 2nd unit will be considered
as domain#3.
| Is This Answer Correct ? | 1 Yes | 4 No |
Answer / prabhakaran
Domain means combination of both FCS and HIS system.
Station means Field control station (FCS).
| Is This Answer Correct ? | 0 Yes | 3 No |
what is PID n give me brief info. about P&I&D.
how to design orifice plate?what is the equation?
How to check loadcell working or notworking
I have one DP transmitter of range 0-500mmWC i have to calculate its range in M3/hr for flow measurement so whats the formula.
what is the difference between SCADA and DCS?
1.what is the role of proportional comtroller in pid controller?2.How do u calibrate the control valve?
whatis range of marcury filled tempereture gague
wHAT IS BURST MODE IN TRANSMITTER?
what difeerent between HART and BRAIN?
A length of steel pipe is used to carry sea water to a desalination plant. An adequate corrosion allowance must be specified and indicated in the piping specification, which affects the _________________________ of the pipe
if a dp transmitter has range 100 in H2O and flow is 20mmcf and if the flow is changed to 25 mmcf then what is the formula to determine new range of transmitter
what is the difference between Cv and air consumption? why the customer needs Air consumption details?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)