1.how to calculate 4*3 runner qty in cft.
2.how to calculate the nails qty.(column,beam,slab)
3.if any formula for binding wire qty calculation.
Answer / ratheesh
1. First you have to convert inches to feet, 1 inch =
.083feet, Then u have to multiple length, breadth & width.
2. approximate .750grms to 1kg for 1 sqm shuttering.
Is This Answer Correct ? | 4 Yes | 3 No |
material requred for 1 square foot lanter with formula
How to calculate the cement and fine aggregate requirement for solid block masonry works in terms of Sqm. 1. 400x200x200mm 2. 400x200x100mm 3. 600x200x100mm 4. 600x200x200mm I need the answer for 1 Sqm of solid block works.
What do you mean by honeycomb in concrete?
what are the grades of concrete?where and or what purpose a particular grade is used in a particular structure?
Explain what is change order request?
Minimum spacing of 2- bars in column, beam, slab
What are the causes of failure of foundations and remedial measures?
What is the graphical relationship between N - Value of soil and Dia. of pile when pile length is fixed, and n - Value and length of pile when its dia. is fixed.
which type of cement is used for RCC construction?Why?
What is the crank length in the slab?
The largest size of paper used in plotter to print the drawing made by Autocad .
beam top main reinforcement(25mm) was drilled off by mistakely when making drill hole for dummy columns. any one can give useful information for this issue or related code or websites.