1.how to calculate 4*3 runner qty in cft.
2.how to calculate the nails qty.(column,beam,slab)
3.if any formula for binding wire qty calculation.

Answer Posted / ratheesh

1. First you have to convert inches to feet, 1 inch =
.083feet, Then u have to multiple length, breadth & width.

2. approximate .750grms to 1kg for 1 sqm shuttering.

Is This Answer Correct ?    4 Yes 3 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

While calculating the weight of the steel per running meter, the formula used is [(dxd)/162]. Why 162 is used in denominator & how it is derived?

1130


The portion of a brick cut across the width is called?

962


What is the difference between built area and super built up area?

683


What Are The Different Type Of Slump Test Indications?

815


IS THERE ANY JOBS FOR THOSE WHO ARE IN FINAL YAER OF ENGINEERING(CIVIL) IN MUMBAI

1590






What are the materials used in building a gravity dam?

645


how to take concrete quantity for precast segment for viaduct project?

2576


The mixture of different ingredients of cement is burnt at?

1099


how much of quantity of material required for execution of one cubic meter of random rubble masonry in 1:3 cement mortar

1918


How to calculate the quantity of ingredients of M20 grade concrete?

1519


Explain how you can use different dimension tools in CAD? What are the different dimensions available?

651


for pretensioning which will yield first and same for post tensioning?

1711


In earth work 1300 cum soil how to calculate how many liters require in water

1999


What is the coeffiencent Friction Angle between Steel and Ashphalt?

2519


what is meant by shear center?????

2141