calculate qty of sand in 15 mm plaster for 100 sqm.
Answers were Sorted based on User's Feedback
wet mortar =100*.015=1.5
dry mortar =1.5*1.2 =1.8
ratio =1:4 (assumed)
sum =1+4=5
sand =4*1.8/5=1.44 cu m (answer)
Is This Answer Correct ? | 32 Yes | 7 No |
Answer / kumar navneet
Unit- 1sqm ; take 100sqm
Qty of mortar req to plaster wall= 100sqm x .015m=1.5cum
To make up for uneveness inc by 30% = 1.5+ (1.5x30)/100= 1.95cum
Inc by 25% the total dry volume = 1.95+ (1.95x30)/100
= 2.34 cum
for 1:4 cement sand mortar (Assumed)
Cement = 2.34/(1+4)= 0.468cum
Sand = 0.468 x 4= 1.872cum
Is This Answer Correct ? | 3 Yes | 1 No |
Answer / qaisar imtiaz
15MM PLASTER FOR 100 SQ.M
THEN TOTAL AREA IS MEAN 10*10=100 SQ.M
10*10*0.015=1.5 CUM
RATIO =1:3
FOR CEMENT =1.5/4*1=0.375/0.0354=10.60 BEG
FOR SAND = 1.5/4*3=1.125CUM
Is This Answer Correct ? | 1 Yes | 2 No |
Answer / er. shivam dixit
15 mm plaster for 100 sq. m.
then the total quantity = 1500 cu. m.
let us consider the cement plaster proportion is 1:4
then the total sum of the proportion = 5
total dry mortar required for 1cu. m. = 0.40
the sand required for one cu. m. = (4*0.40)/5 = 0.32 cu. m.
so the total sand required 15mm plaster for 100 sq.m.
= 15*100*0.32 = 480 Cu.m.
Is This Answer Correct ? | 2 Yes | 36 No |
What is the per cu. mt. price of ready mix in Gujarat region.?
In cement concrete how to check a quality of material also proportion of material at site ?
Why provide strripus in a column minimum and maximum spacing.
what is mean by bulking of sand?
11 Answers CCCL, Kanakia Group,
Suggest how many column, beem, etc required for 30 mtrs x 21 mtrs width x 8mtrs height for industrial shed of ground floor. I want to know the quantity of tmt steel consumption and Concrete consumption for budgeting
0 Answers Vishal Pipeline And Engineering,
how to calculate round stirrups.
4 Answers Infinity Engineering,
Our IDCT industrial cooling tower height is 15 mtres so need to RCC structure stability test as par any IS Standard or Indian act.
For what purpose bedding is used under storm water drains, explain?
What is the acceptance criteria to determine the "Core density" of "DBM or BC" course,for any grade as per "MORTH" guidelines in road construction work ?
What is the mixing of D.P.C?
when we workout quantities of reinforcement steel , whate are the critari of lap length for column
How many different between estimated quantity and practical work at site.