Where is lap in top & bottom beam
Answer / amit soni
1.Top Reinforcement laps not provide in Near Column because Shear force heavy in Junction.Provide Top Bar Lap in center of Clear Span.
2.Just Opposite Bottom Reinforcement lap not Provide in Center of Clear Span because their bending force is heavy. Provide Bottom Lap Near Column where bending force Minimum.
Is This Answer Correct ? | 28 Yes | 1 No |
whats is the Indian standard ratio for mix design M5 M10 M15 M20 M25 M30 M35 AND M40???
what is Quality Reporting?
where does the hinged action while designing the strture
Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quantity of concrete by explaining all formulas involved.
16 Answers Reliance, Siddhi Constructions,
how to read the drawings to find the quantity of steel in a storm water manhole or any other structure?
Minimum and maximum size of the building components
Is there any difference in IS 456 and IRC 15?
show answer/ calculate-1-2-4 ratio-concrete -cement-sand- metal-water - please brief calculation
Dear Frds, How can i calculate the Steel for RCC Slab, Please provide one Example also, so that i can understand very well. Ex: Area: 1320.0 Sft.(44' X 30') Span: 15'(Default). Column Size: 9"X15"(6 No.s 12mm Rods) Please Provide Calculation Details. Thankyou. Satish
number of standard bricks need 1 cubic meter
percentage of wastage limits in construction materials EX : min & max . cement = fine aggregate = coarse aggregate = admixture = wood = tiles = painting = marbles = bricks =
Actually i am confused that how to calculate the bending moment for a semi-circular beam and curved slab.If any one have a good idea about the matter,please give the answer with a suitable example. Thank you......