how to calculate concrete quantity for footing using M25 grade
1:1:2 for 730cft.
Answers were Sorted based on User's Feedback
Answer / kuldeep singh sevariya
dry quantity of 1 cum wet concrete =1.54
730cft=20.67cum of wet quentity
so,dry quentity of 20.67cum=1.54*20.67=31.83cum
CEMENT=(31.83*1)/(1+1+2)=7.96cum
(Density of cement-1440kg/cum)
(7.96*1440)/50=229.176Bags
SAND=(31.83*1)/4=7.92CUM, SO, 1600*7.92=12672 KG
AGGREGATE=(31.83*2)/4=15.92 CUM
SO,1520*15.92=24198.4 KG
| Is This Answer Correct ? | 14 Yes | 3 No |
Answer / mohammed aijaz hussain
Volume of Wet concrete = 730 cu.ft. = 20.68 cu.m.
Volume of Dry concrete = 1.75 X 20.68 = 36.19 cu.m.
Volume of cement = 1/4 X 36.19 = 9.048 cu.m.
= 258.5 Bags
Volume of Sand = 1/4 X 36.19 = 9.048 cu.m.
Volume of Aggregate = 2/4 X 36.19 = 18.095 cu.m.
| Is This Answer Correct ? | 5 Yes | 2 No |
What is the cost of formwork for columns/beams/rcc walls also what is the cost of shuttering for roof slab at height of 25 feet
how can we calculate the quantity of cement, sand, aggregate in any concrete mix
Is it possible to make a feature using an overdefined sketch?
how many kg reinforcement is required for G+ 1 roof slab of 1200qf slop slab with 5 inch thickness of house.
1.why can't we used sea sand in construction? 2.can we change sea sand into normal sand? if yes how?
satart to end steps by step process of building construction...? i want to planning theme accuretly
why canot DBM is continue as surface coarse insted of BC? what is dieefrence between DBM & BC?
what is the sequence of the activities in the typical under ground water tank including civil & MEP works.
How to correct a column which don't have sufficient cover?
How many number of bars used in circular columns? Explain WHY?
Do you expect there to be many jobs for civil engineers going into the future? What are the three main drawbacks of being a civil engineer? What are the three best things about being a Civil engineer? What amount of vacation time is available to you? Is the time paid? What are the usual hours of work required? Is it possible, or common, to work from home? How much time do you spend on the site of your projects? What type of schooling is required to be a civil engineer? How many years are required to complete this education?
What do you mean by the word 'shear'?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)