During the testing of Electrical Equipment the test cables
should not touch the equipments. For that testing engineers
use to cotton rope to hang the cable from measuring
Equipment to testing equipment terminal. Please explain the
technical reason for this practice.



During the testing of Electrical Equipment the test cables should not touch the equipments. For tha..

Answer / k.prakashchandra

This is done while meggering ,so that the measured value
will not be less, due to the proximity of cable with the body.

Is This Answer Correct ?    3 Yes 0 No

Post New Answer

More Electrical Engineering Interview Questions

working principal of online ups

0 Answers   Delta Power Systems,


transformer phasor diagram under load explain it?

0 Answers  


What is the role of the 50 STUB protection at a GIS 400KV substation with SIEMENS protection relays?

0 Answers   Power Plant,


What is mean by hormonics?

5 Answers  


What are the voltage values for LT,HT,EHT and other voltages??

22 Answers   INEL, MNC,






what u meant of power plant?

5 Answers  


what kind of material to be used after ngr unit? cu or GI

1 Answers   Michelin,




0 Answers   Maples,


What types of I/O have you designed? What were their size? Speed? Configuration? Voltage requirements? Process technology? What package was used and how did you model the package/system? What parasitic effects were considered?

0 Answers  


How electrical power(MW)is varied OF an A.C Generator in response to varying steam input to a steam turbine ?

1 Answers   Hindalco,


i am swathi, b.tech 4th year. In smps(switched mode power supply)we are using diodes,mosfets,igbts for controling of current. And my question is why we did not use thyristors(scr)? it is also act as a switch,then what is the drawback of scr as compared to above transisters> if we use the scr,then what is happening ? plz give reply as soon as possible bcoz i am doing project on smps. plz frnds i want ans for that. if anybody know the ans plz send to my e-mail id /swathi.tadakapally@gmail.com/

5 Answers   EEE, TCS,


what r the checklist while installing a 380 kva DG set

0 Answers   Pepsi,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)