Answer / aamod tripathi.
Commissioning a distribution transformer knowing all its
rating, Transformation ratio, Vector group, Phase sequence
is a skilled Job. You will need the information of complete
system like where the distribution transformer you are
talking about comes.
Information needed will be,
1. Single Line Diagram of the complete circuit (So as to
clearly understand the vector group/ rating of the
transformer to be installed, if there are many distribution
transformers to be installed in a locality).
2. Transformer foundation drawings and the drawings of
Bolts where the transformer will be bolted.
3. Whether to be installed on ground/ On pole
4. Whether oilfilled/ Drytype.
5. If oil filled provision of soakpit and clearances from
firewall.
6. If conservator tank and radiators are there the clearances
7. Provision for grounding.
8. All drawings of transformers from all angles.
Is This Answer Correct ? | 6 Yes | 0 No |
why DG battery blast
Why we check only first column of root locus..?
defination of controlled shunt reactor
i need bhel question papers.
what is the advantage of DC Motor over AC motor & Where its applicable ?
how to determine the size of power cable according to load current
What should be the setting of an earth fault relay.
why induction motor take more current when motor start time and this current take for 1 hours when motor is start.
What will be the effect of circulating current in HT xlpe cable when both the armour ends are grounded. Will the termination fils after some time in case of 33 kv supply.
11Kv Dog conductor 6/0.186 formula Line Losses ? Length 4.85Km amper ..? 52 Pole Max Load 3200Kw
how to create new innovation what are the supporting sources in the electrical field for Electrical engineers.....?
Is there any difference between circuit breakers and isolators