in 400 kv system why should trip both side CB when we give
hand trip?
Answer / k.prakashchandra
Hand trip means issuing 'line clear' ?.In case of tr lines
connected to network at both ends ,it is necessary to obtain
NFBC( no feed back certificate) from the other end to issue
line clear or permit to work.
| Is This Answer Correct ? | 26 Yes | 3 No |
how can the active power and reactive power of an alternator be controlled?
Is voltage & potential transformer are the same? Are they used for same application ?
What is the formula to find out two phase active & reactive power
We operate a 10 Mw facility and we have been experiencing several trips due to fluctuations on the MVAR? We have checked all issues related to the AVR and we have found all OK? Can anyone help us? The grid voltage, internal voltage, all regular parameters look ok. MVAR fluctuate and there it goes the unit? What could be happening? Thanks!
What will be the voltage impact on secondary side of two transformers with different vector groups when both voltages are compared.
how speed control of induction motor?
what is skin effect and why is it absent in DC systems
In wat way the power compensation takes place when a statcom is connected in a transmission line
what is entropy?
Why slip ring ind. motor power consumption is low compare to induction motor .same 90 kw motor used same load output
Which one hurts more AC or DC Current ?
What is the emf equation of a transformer?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)