in 400 kv system why should trip both side CB when we give
hand trip?
Answer / k.prakashchandra
Hand trip means issuing 'line clear' ?.In case of tr lines
connected to network at both ends ,it is necessary to obtain
NFBC( no feed back certificate) from the other end to issue
line clear or permit to work.
Is This Answer Correct ? | 26 Yes | 3 No |
how is the magnetic current test is different in delta-star and delta delta transformer.
please send me the L&T Emb. sys. placement papers and entire details of pattren
HT/LT TRANSFORMER TEST?
whats the application of voltage regulation? and whats the voltage regulation's device?
why ss stablity limit is more transient stablity limit?
how we can do the insulation on secondary of ct explain and so that tan delta will within limit
why overcurrent fault occurs in power system.
LT cable fault checking instrument is available? where and how to get it.
no EB power DG is not starting?
The unit of quantity of electricity is the:(a) volt(b) coulomb(c) ohm(d) joule
what is the profesional board for electrical engineer what is thepast and during construction for electrical engineering
HOW MUCH CURRENT CAN A 3 -1/2 CORE 100 MM WIRE CARRY